FIR13-00661
| INSP-Sprinkler Rough-in/Hydro | 2/14/2014 | 2/14/2014 | 2/14/2014 4:41:37 PM | P | PART |
|
|
|
FIR13-00694
| INSP-Sprinkler Rough-in | 2/14/2014 | 2/14/2014 | 2/14/2014 4:36:19 PM | P | PART |
|
|
Okay to cover overhead fire sprinkler work at the grid ceiling areas. Verified 401 coverage at restroom partitions. Need to remove foil at gym area upright heads.
|
FIR13-00664
| INSP-Sprinkler Rough-in/Hydro | 2/13/2014 | 2/14/2014 | 2/14/2014 4:25:57 PM | A | PART |
|
|
Overhead hydrostatic testing for both wet systems passed. Need to provide 1st floor office area plans, missing flexible couplings at the base of the risers.
|
BLD13-01691
| FIRE-Final Inspection | 2/13/2014 | 2/14/2014 | 2/14/2014 2:04:44 PM | A | PASS |
|
|
Previous C/N items verified for completion. Fire life safety passed.
|
FIR13-00704
| INSP-Sprinkler Rough-in/Hydro | 2/13/2014 | 2/14/2014 | 2/14/2014 1:59:57 PM | A | PART |
|
|
Overhead hydrostatic testing passed. Noted spacing adjustments will be necessary at the east side offices and classrooms.
|