Inspections for the day of: Wednesday, February 14, 2018.
Number of inspections: 19
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorDan Ediger
TitlePLM-INSPECTOR
Phone #869-5166
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
PLM17-01549 DOC - Permit Finaled2/14/20182/14/20182/14/2018 3:38:49 PMPPASS
PLM17-02968 Final2/14/20182/14/20182/14/2018 3:32:03 PMPPASS
we prefer later in the day if possible.

thanks,
Phone #: ###-#### Inspection requested via web by Nicholas Paige
PLM17-01432 Plumbing Rough-in2/13/20182/14/20182/14/2018 2:54:49 PMPPART
Plumbing Rough In for Commercial Tower. If there are any questions please contact Larry J. at ###-#### Phone #: ###-#### Inspection requested via web by Stacia . Haumann.
Roof and deck drains ok
PLM17-01433 Final2/13/20182/14/20182/14/2018 2:54:17 PMPPASS
Plumbing Final for Admin Building. If there are any questions please contact Larry J. at ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann
PLM17-05065 Final2/14/20182/14/20182/14/2018 2:16:21 PMPPASS
Drinking fountain is set Phone #: ###-#### Inspection requested via web by bob pond
PLM18-00636 Plumbing Rough-in2/13/20182/14/20182/14/2018 2:01:07 PMPFAIL
Contact Name: Roger Elam Phone #: ###-#### requested via web by Melissa Kaae.
The new sink requires a 2" drain.
PLM18-00635 Final2/14/20182/14/20182/14/2018 1:44:23 PMPPASS
we prefer later in the day if possible.

thanks Phone #: ###-#### Inspection requested via web by Nicholas Paige
PLM18-00621 Plumbing Rough-in2/13/20182/14/20182/14/2018 11:40:14 AMPNR
Phone #: ###-#### Inspection requested via web by Branden Steers
PLM18-00613 Plumbing Rough-in2/13/20182/14/20182/14/2018 11:14:07 AMAPASS
Anthony Phone #: ###-####
PLM18-00631 Plumbing Rough-in2/13/20182/14/20182/14/2018 11:05:31 AMAPASS
Phone #: ###-#### Inspection requested via web by John Hensley
PLM18-00631 DOC - Permit Finaled2/14/20182/14/20182/14/2018 11:05:21 AMPPASS
complete
PLM16-00054 PLM-Aging Inspection2/14/20182/14/20182/14/2018 10:50:06 AM PEND
wip
PLM17-04416 Final2/13/20182/14/20182/14/2018 10:49:26 AMAPASS
Phone #: ###-#### Inspection requested via web by Ann Marie Reyes
PLM18-00507 Final2/14/20182/14/20182/14/2018 10:32:40 AMAPASS
PLM18-00313 Final2/13/20182/14/20182/14/2018 10:03:24 AMAFAIL
TI FINAL TRIM INSPECT Phone #: ###-#### Inspection requested via web by Chris Field.
1. Run the t&p drain to the floor sink w/ a 1-1/2"
air gap.
2. Install an expansion tank for the water heater.
3. Install tempering valve on the public lav faucets.
PLM18-00091 Plumbing Rough-in2/13/20182/14/20182/14/2018 9:33:47 AMAPASS
Danielle Phone #: ###-####
PLM17-05032 Groundwork2/13/20182/14/20182/14/2018 9:21:37 AMAPART
DAVID IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER.
Parthial West ground work.
PLM18-00601 Final2/9/20182/14/20182/14/2018 8:36:17 AMAPASS
Old Chicago Pizza Job. Please do inspection at 8am if possible so Master Excavation can complete their portion shortly after. Scott w/ Master Excavation is your contact for the permit ###-#### Phone #: ###-#### Inspection requested via web by Scott Ferguson
PLM15-01767 PLM-Aging Inspection2/14/20182/14/20182/14/2018 8:22:11 AM PEND