Inspections for the day of: Thursday, February 15, 2007.
Number of inspections: 13
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMike Kinnear
TitleELE-INSPECTOR
Phone #794-1379
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE07-00536 Temporary Service2/15/20072/15/20072/15/2007 3:27:34 PMPPASS
John; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt t/s u/g n ok
ELE06-04393 Final2/14/20072/15/20072/15/2007 1:53:38 PMPPASS
CONTACT: JOHN OSTOLASA Phone #: ###-#### ok final
ELE06-03738 Electrical Rough-In2/15/20072/15/20072/15/2007 1:06:03 PMPPART
troy - cover inspect; Phone #: ###-#### Internet Inspection Request from: Victoria Beall ok cover under slab conduit
ELE07-00530 Rough-In Permanent Service2/14/20072/15/20072/15/2007 10:46:42 AMAPASS
Pat, This is a large home. I have another inspection on ridgecrest in this same area scheduled for the afternoon. This inspection can be done any time today. Thanks, heath Phone #: ###-#### ok cover ri p/s u/g n ok
ELE07-00512 Permanent Service2/14/20072/15/20072/15/2007 10:16:21 AMAPASS
Phone #: ###-#### p/s u/g n ok
ELE06-02032 Electrical Rough-In2/15/20072/15/20072/15/2007 10:03:27 AMPCANC
BILL; Phone #: ###-#### Internet Inspection Request from: Victoria Beall Inspection cancelled from web by: Victoria Beall
ELE07-00402 Final2/14/20072/15/20072/15/2007 9:46:04 AMAPASS
sam; Phone #: ###-#### Internet Inspection Request from: Victoria Beall ok final
ELE06-04603 Final2/14/20072/15/20072/15/2007 9:45:18 AMAPASS
sam; Phone #: ###-#### Internet Inspection Request from: Victoria Beall ok final
ELE06-02407 Final2/15/20072/15/20072/15/2007 9:22:16 AMAPASS
ready for Final. outside pole lighting was the only thing left to finish. That is now complete, thank you. I beleive MIke K had allready checked the inside and exterior of building. Phone #: ###-#### ok final note no card available
ELE06-04136 Permanent Service2/14/20072/15/20072/15/2007 9:01:23 AMAPASS
service damage reinspection fee p/s u/g reconnect ok note need to look at inside panel at final
ELE06-03422 Final2/15/20072/15/20072/15/2007 8:50:36 AMAPASS
Final inspection of clean room tool install in building 26 for SUP 03 ###-####. Phone #: ###-#### ok final
ELE06-03332 Final2/13/20072/15/20072/15/2007 8:50:00 AMAPASS
supervisor 02, rkpeterson, call ###-#### Phil Stevenson with any questions. This is to close out old Blanket permit. all wo''s have been looked at previously. just need to final and issue out a new one. thanks Phone #: ###-#### ok final
ELE06-04691 Electrical Rough-In2/14/20072/15/20072/15/2007 8:49:15 AMAPART
Request inspection of a 125 H.P. VFD installation in building 15 on SUP 03 blanket permit. ###-#### Phone #: ###-#### looked at area for motor controll ok disconnect not installed yet