Inspections for the day of: Friday, February 15, 2008.
Number of inspections: 22
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR07-00467 INSP-Final Inspection2/15/20082/15/20082/15/2008 6:12:01 PMPPASS
Fire alarm permit finaled.
BLD06-00450 BLD-Final2/15/20082/15/20082/15/2008 6:11:09 PMPFAIL
Pending repair of the air handler controls at the fire command center.
FIR07-00704 INSP-Final Inspection2/13/20082/15/20082/15/2008 4:30:19 PMPFAIL
Completed test of new fire alarm panel. Found that strobes in corridors were not in-sync and existing strobes in hallways were at 79 inches. As per Sam no changes will need to be made to existing strobes.All other testing per permit Final.
FIR07-00854 INSP-Sprinkler Rough-in2/14/20082/15/20082/15/2008 4:18:35 PMPPART
Remainder of of uderground piping ok to cover.KR
FIR07-00606 INSP-Sprinkler Rough-in2/14/20082/15/20082/15/2008 3:49:12 PMPPART
Inspection for retaining straps at beam clamp hangers prior to cover at the band, choir and practice rooms including the adjacent restrooms.
FIR07-00767 INSP-Final Inspection2/14/20082/15/20082/15/2008 3:07:36 PMAPASS
Corrections verified for compliance, final inspection passed, permit finaled.
BLD07-02576 FIRE-Final Inspection2/14/20082/15/20082/15/2008 2:09:33 PMPFAIL
Need amendments to the fire alarm system completed and remainder of finishes in place for fire life safety acceptance.
BLD08-00060 FIRE-Final Inspection2/14/20082/15/20082/15/2008 2:04:44 PMPNR
Project is not in condition for final fire life safety acceptance, also need project related fire sprinkler and alarm permit finals prior.
FIR07-00465 INSP-Final Inspection2/15/20082/15/20082/15/2008 2:02:27 PMPPASS
Fire alarm permit finaled.
FIR08-00046 INSP-Final Inspection2/15/20082/15/20082/15/2008 2:00:49 PMPPASS
Fire alarm permit finaled.
FIR07-00467 INSP-Alarm Testing2/15/20082/15/20082/15/2008 1:56:25 PMAPASS
Site fire alarm testing completed.
FIR07-00465 INSP-Alarm Testing2/15/20082/15/20082/15/2008 1:55:33 PMAPASS
Fire alarm testing completed satisfactory.
FIR07-00029 INSP-Final Inspection2/13/20082/15/20082/15/2008 1:52:25 PMAPASS
Fire sprinkler permit approved for final.
FIR07-00140 INSP-Final Inspection2/13/20082/15/20082/15/2008 1:51:15 PMAPASS
Fire sprinkler work passed final inspection, one missing escutcheon installed while on site, permit finaled.
FIR07-00141 INSP-Final Inspection2/13/20082/15/20082/15/2008 1:49:55 PMAPASS
Painted escutcheons at two locations replaced while on site, as-built plans accepted, permit finaled.
FIR08-00097 INSP-Sprinkler Rough-in2/14/20082/15/20082/15/2008 1:47:45 PMAPART
OH system modifications are good for cover per the scope of permit work.
FIR07-00977 INSP-Sprinkler Rough-in2/14/20082/15/20082/15/2008 1:45:42 PMAPART
Conference room heads at the drop ceiling are approved for cover.
FIR08-00025 INSP-Sprinkler Rough-in2/14/20082/15/20082/15/2008 1:44:39 PMAPART
Okayed cover at the hard lid ceilings for the elevator lobby- see area indicated on plans, also verified items from previous inspection.
BLD08-00180 FIRE-Final Inspection2/15/20082/15/20082/15/2008 11:49:34 AMAPASS
Door hardware repair verified per D. Hannah, fire life safety passed.
BLD06-00456 FIRE-Final Inspection2/14/20082/15/20082/15/2008 10:32:00 AMAPASS
Items on correction notice verified for completion, fire life safety finaled.
FIR07-00906 FIR-Aging Inspection2/15/20082/15/20082/15/2008 10:12:45 AM DONE
Construction underway, work in progress.
FIR07-01008 INSP-Final Inspection2/14/20082/15/20082/15/2008 12:00:00 AMACANC
Scheduled by a contractor via Hello! on 2/14/2008 at 4:54:22 PM. Contact: ###-####. - brian w simplex/grinnel called to cancel at 10:45 am