BLD17-03573
| BLD-Framing/Rough-in | 2/15/2018 | 2/15/2018 | 2/15/2018 3:33:50 PM | P | PASS |
|
|
Tim Bosier Phone #: ###-####
|
BLD17-01950
| BLD-Framing/Rough-in | 2/15/2018 | 2/15/2018 | 2/15/2018 2:56:11 PM | P | PART |
|
|
Ken Phone #: ###-#### rated wall center of building wip gyp screw pick up base plate/butts/ ele back to back need fire stopping
|
BLD18-00157
| BLD-Foundation | 2/14/2018 | 2/15/2018 | 2/15/2018 2:11:45 PM | P | PASS |
|
|
Mat footing on GL-2 between J;K. Stem walls on GL-2 between D;H. Stem walls on GL-5 between F;L. Stem walls on GL-4 between L;N. Phone #: ###-#### Inspection requested via web by Kevin Honeycutt
|
BLD17-04103
| BLD-Framing/Rough-in | 2/15/2018 | 2/15/2018 | 2/15/2018 1:52:26 PM | P | PASS |
|
|
Collins Engineers Phone #: ###-#### Inspection requested via web by Mark Steen
|
BLD17-03813
| BLD-Footing | 2/13/2018 | 2/15/2018 | 2/15/2018 1:24:10 PM | P | PASS |
|
|
Requesting 12:00 noon inspection time as we are trying to schedule a concrete pour Phone #: ###-#### Inspection requested via web by Ken Olsen
|
BLD16-00936
| BLD-Final | 2/14/2018 | 2/15/2018 | 2/15/2018 10:27:28 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Hans Weikl
|
BLD17-02871
| BLD-Foundation | 2/14/2018 | 2/15/2018 | 2/15/2018 10:21:31 AM | A | PASS |
|
|
rebar // John Phone #: ###-#### mti/si pending report to 450
|
BLD17-03554
| BLD-Aging Inspection | 2/15/2018 | 2/15/2018 | 2/15/2018 9:09:00 AM | | PASS |
|
|
Expires: 04/01/18 ncfi
|
BLD17-02427
| BLD-Framing/Rough-in | 2/15/2018 | 2/15/2018 | 2/15/2018 8:54:50 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by David Scaggs
|