BLD18-03923
| FIRE-Final Inspection | 2/15/2019 | 2/15/2019 | 2/15/2019 4:17:40 PM | P | PART |
|
|
Life fire safety inspection for level 4 complete. Stairwells to remain clear with no storage once TCO is authorized.
|
BLD18-04246
| FIRE-Final Inspection | 2/15/2019 | 2/15/2019 | 2/15/2019 3:48:49 PM | P | DONE |
|
|
Life fire safety inspection passed per Troy's notes on 05FEB2019.
Tony Phone #: ###-####
|
BLD18-04376
| FIRE-Final Inspection | 2/15/2019 | 2/15/2019 | 2/15/2019 3:48:04 PM | P | PASS |
|
|
Life fire safety inspection for vanilla spaces complete, no occupancy allowed under this permit per project notes.
Tony Phone #: ###-####
|
BLD18-03882
| FIRE-Final Inspection | 2/14/2019 | 2/15/2019 | 2/15/2019 3:11:22 PM | P | PASS |
|
|
No fire sprinklers, no fire alarms, fire extinguishers are placed with current inspection tags, thumbturn deadbolts on main entry doors to be replaced with double keyed deadbolts or the inside lock function will be removed so only the key function works outside to secure door, deadbolt changes to be completed before final BLD inspection. Final life fire safety inspection for area of work complete.
Tammera Phone #: ###-####
|
BLD17-00386
| FIRE-Final Inspection | 2/15/2019 | 2/15/2019 | 2/15/2019 2:33:07 PM | P | PART |
|
|
Life fire safety inspection for Phase 3 complete. Will need to have access control comply with chapter 10 of IFC before final inspection of project.
Please call when at the gate Phone #: ###-#### Inspection requested via web by Harvey VanderVeen
|
FIR17-00626
| INSP-Alarm Testing | 2/15/2019 | 2/15/2019 | 2/15/2019 2:31:59 PM | P | PART |
|
|
Fire alarm testing for phase 3 complete, LF sound bases in rooms were a steady tone when alarms are active, LF bases need to be temporal 3 with the rest of the system, temporal sound fo LF bases will need to be verified at final inspection.
After 1PM if possible. Phone #: ###-#### Inspection requested via web by Gary Gambino
|
FIR18-00680
| INSP-Sprinkler Rough-in/Hydro | 2/14/2019 | 2/15/2019 | 2/15/2019 1:49:28 PM | P | PART |
|
|
Hydrostatic test for levels 1 and 2 overehad fire sprinkler piping witnessed, no pressure loss observed, no other inspections were perfromed.
Call Anthony before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
BLD18-02700
| FIRE-Final Inspection | 2/14/2019 | 2/15/2019 | 2/15/2019 1:31:43 PM | P | FAIL |
|
|
FIR permit for fire sprinklers needs to be finaled before life fire safety can be completed.
Shane Phone #: ###-####
|
FIR19-00012
| INSP-Final Inspection | 2/14/2019 | 2/15/2019 | 2/15/2019 1:31:06 PM | P | FAIL |
|
|
Dry pipe valve needs to be serviced, clapper did not open with inspectors test flow.
Phone #: ###-#### Inspection requested via web by jeremiah robison
|
BLD18-03686
| FIRE-Final Inspection | 2/15/2019 | 2/15/2019 | 2/15/2019 10:33:37 AM | A | CANC |
|
|
Due to scheduling we could not coordinate time for life fire safety inspection, request will need to be rescheduled for a later date, this request is cancelled.
Jim, call 1/2 hr prior to arrival. Meet in B26 lobby. Thanks Phone #: ###-#### Inspection requested via web by Daniel Cook
|
BLD18-03923
| FIRE-Final Inspection | 2/14/2019 | 2/15/2019 | 2/15/2019 10:07:57 AM | A | FAIL |
|
|
Left a voicemail with point of contact provided, waited for 30 minutes to recieve a return call, no return call was made, proceeded to next inspection, this request will need to be rescheduled.
Steve- wants partial on the 4th floor for a temp c of o Phone #: ###-####
|
BLD19-00429
| FIRE-Final Inspection | 2/14/2019 | 2/15/2019 | 2/15/2019 9:34:45 AM | A | PASS |
|
|
No fire sprinkler modifications, no fire alarm modifications, fire extinguisher is placed with a current inspection tag. Final life fire safety inspection for area of work complete.
Matt Phone #: ###-####
|
BLD19-00428
| FIRE-Final Inspection | 2/14/2019 | 2/15/2019 | 2/15/2019 9:34:28 AM | A | PASS |
|
|
No fire sprinkler modifications, no fire alarm modifications, fire extinguisher is placed with a current inspection tag. Final life fire safety inspection for area of work complete.
Matt Phone #: ###-####
|
NAF18-00124
| INSP-Supply line flush | 2/13/2019 | 2/15/2019 | 2/15/2019 9:10:01 AM | A | DONE |
|
|
Underground main line flush complete.
Call prior to going Phone #: 2082799090 >> Inspection requested via mobile web by Ken
|
FIR18-00673
| INSP-Sprinkler Rough-in | 2/14/2019 | 2/15/2019 | 2/15/2019 7:30:05 AM | A | PART |
|
|
Rough to cover inspection for overhead fire sprinkler piping above hardlids in corridor complete, corridors approved for cover.hallway // Todd Phone #: ###-####
|
FIR18-00966
| INSP-Final Inspection | 2/14/2019 | 2/15/2019 | 2/15/2019 7:10:35 AM | A | FAIL |
|
|
Speaker strobe in elevator lobby outside the scope of work did not operate. Sound on floor from speaker strobes did not meet the sound requirements, need to make neccessary changes to increase sound volume, could barely hear audible alarm when office doors were closed.
This is scheduled for 7:00 am Phone #: ###-#### Inspection requested via web by Sam Ball
|
FIR18-00922
| INSP-Final Inspection | 2/14/2019 | 2/15/2019 | 2/15/2019 7:07:05 AM | A | PASS |
|
|
Final fire sprinkler inspection for area of work complete.
This is scheduled for 7:00am Phone #: ###-#### Inspection requested via web by Sam Ball
|
BLD17-00386
| FIRE-Final Inspection | 2/14/2019 | 2/15/2019 | 2/15/2019 7:02:23 AM | A | CANC |
|
|
Please call when at the gate. Phone #: ###-#### >> Inspection requested via web by Harvey VanderVeen Inspection cancelled from web by: Harvey VanderVeen
|