BLD99-03410
| BLD-Final | 2/15/2000 | 2/16/2000 | 2/16/2000 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 02/15/2000 at 13:25:55. Contact: ###-####. L/C issued. 2/16/00 11:50:35 AM
|
BLD99-03694
| BLD-Framing/Rough-in | 2/15/2000 | 2/16/2000 | 2/16/2000 12:00:00 AM | A | FAIL |
|
|
Jay ###-#### See C/N. 2/16/00 11:50:48 AM
|
MEC99-04040
| Final | 2/15/2000 | 2/16/2000 | 2/16/2000 12:00:00 AM | A | PASS |
|
|
after 9:00\\###-####
|
MEC00-00318
| Rough-in | 2/15/2000 | 2/16/2000 | 2/16/2000 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 02/15/2000 at 16:18:15. Contact: ###-####.
|
MEC00-00318
| Pressure Test | 2/15/2000 | 2/16/2000 | 2/16/2000 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 02/15/2000 at 16:18:40. Contact: ###-####.
|
BLD00-00260
| BLD-Foundation | 2/15/2000 | 2/16/2000 | 2/16/2000 12:00:00 AM | A | PART |
|
|
###-####\\wall Forms incomplete 2/16/00 11:49:51 AM
|
BLD00-00225
| BLD-Foundation | 2/15/2000 | 2/16/2000 | 2/16/2000 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 02/15/2000 at 20:00:05. Contact: ###-####. Incomplete rebar ok. 2/16/00 11:50:01 AM
|
BLD99-02911
| BLD-Foundation | 2/16/2000 | 2/16/2000 | 2/16/2000 12:00:00 AM | P | PASS |
|
|
###-#### ready at 2
|
BLD99-01688
| BLD-Wall cover | 2/16/2000 | 2/16/2000 | 2/16/2000 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 02/16/2000 at 10:47:45. Contact: ###-####. Need detail for metal beam and connections. 2/17/00 9:07:48 AM
|
BLD98-03724
| BLD-Framing/Rough-in | 2/16/2000 | 2/16/2000 | 2/16/2000 12:00:00 AM | P | PART |
|
|
###-#### 2 hr wall incomplete. 2/17/00 9:07:57 AM
|
BLD99-01841
| BLD-Other | 2/16/2000 | 2/16/2000 | 2/16/2000 12:00:00 AM | P | FAIL |
|
|
Scheduled by a contractor via Hello! on 02/16/2000 at 10:54:09. Contact: ###-####. No plan no ans on phone. 2/17/00 9:08:07 AM
|