FIR16-00797
| INSP-Supply line flush | 2/16/2017 | 2/17/2017 | 2/17/2017 3:31:16 PM | P | DONE |
|
|
Underground main line flush complete
|
FIR16-00299
| INSP-Sprinkler Rough-in | 2/16/2017 | 2/17/2017 | 2/17/2017 1:27:24 PM | A | PASS |
|
|
Rough to cover inspection for overhead fire sprinkler piping/pendant heads in hotel rooms on level 4 complete, hotel rooms on level 4 approved for cover.
|
FIR16-00223
| INSP-Sprinkler Rough-in | 2/16/2017 | 2/17/2017 | 2/17/2017 8:41:52 AM | A | PART |
|
|
Rough to cover inspection for overhead fire sprinkler piping/installed pendant heads in suspended ceiling area's located on level 2, middle open section and rooms along the exterior walls to exlude the northside rooms (ceiling grid was not installed at time of inspection) complete, approved for cover.
|