FIR13-00377
| INSP-Final Inspection | 2/18/2014 | 2/18/2014 | 2/20/2014 10:12:06 AM | P | PASS |
|
|
Permit finaled.
|
FIR13-00575
| INSP-Final Inspection | 2/17/2014 | 2/18/2014 | 2/20/2014 9:33:29 AM | P | PASS |
|
|
Fire sprinkler permit finaled.
|
BLD13-02957
| FIRE-Final Inspection | 2/18/2014 | 2/18/2014 | 2/18/2014 4:25:50 PM | P | PASS |
|
|
Final okay pending egress components per approved plans- to be verified at structural final.
|
FIR14-00090
| INSP-Final Inspection | 2/14/2014 | 2/18/2014 | 2/18/2014 4:19:32 PM | P | NR |
|
|
Robert Phone #: ###-#### *Pending project related work
|
FIR14-00009
| INSP-Final Inspection | 2/14/2014 | 2/18/2014 | 2/18/2014 4:16:05 PM | P | NR |
|
|
Trade work not in condition for final at this time.
|
BLD08-00379
| FIRE-Final Inspection | 2/14/2014 | 2/18/2014 | 2/18/2014 4:14:10 PM | P | PASS |
|
|
C/N items verified for completion. Scope of work finished. Fire life safety finaled.
|
BLD13-03415
| FIRE-Final Inspection | 2/18/2014 | 2/18/2014 | 2/18/2014 4:08:39 PM | P | PASS |
|
|
Fire life safety inspection completed acceptable.
|
FIR14-00042
| INSP-Final Inspection | 2/14/2014 | 2/18/2014 | 2/18/2014 1:37:33 PM | A | PASS |
|
|
Scope of fire sprinkler work completed and passed final inspection. Permit finaled.
|
FIR13-00730
| INSP-Final Inspection | 2/13/2014 | 2/18/2014 | 2/18/2014 12:49:24 PM | A | PASS |
|
|
Fire alarm testing completed satisfactory. Permit finaled.
|
FIR13-00308
| INSP-Sprinkler Rough-in/Hydro | 2/14/2014 | 2/18/2014 | 2/18/2014 12:14:36 PM | A | DEFR |
|
|
Leroy is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus
|
BLD13-03479
| FIRE-Final Inspection | 2/17/2014 | 2/18/2014 | 2/18/2014 12:13:59 PM | A | PART |
|
|
Final pending remainder of remodel work at the SW offices. North office area okayed.
|
FIR13-00577
| INSP-Sprinkler Rough-in | 2/14/2014 | 2/18/2014 | 2/18/2014 12:01:26 PM | A | PART |
|
|
Okay to cover overhead work at the remodel area drop ceilings.
|
BLD13-02957
| FIRE-Final Inspection | 2/14/2014 | 2/18/2014 | 2/18/2014 12:00:05 PM | A | NR |
|
|
Missing approved plans on site, may need to provide an additional exit sign.
|
FIR14-00029
| INSP-Final Inspection | 2/13/2014 | 2/18/2014 | 2/18/2014 11:58:21 AM | A | PASS |
|
|
Fire alarm testing passed, permit finaled.
|
FIR14-00021
| INSP-Final Inspection | 2/17/2014 | 2/18/2014 | 2/18/2014 11:56:27 AM | A | PART |
|
|
Remainder of fire sprinkler work completed- Final pending field ceiling tile installation.
|
FIR13-00582
| INSP-Sprinkler Rough-in | 2/14/2014 | 2/18/2014 | 2/18/2014 11:55:12 AM | A | PART |
|
|
Grid ceiling areas okayed for cover.
|
FIR13-00661
| INSP-Sprinkler Rough-in | 2/17/2014 | 2/18/2014 | 2/18/2014 11:54:25 AM | A | PART |
|
|
Okay to cover overhead fire sprinkler modifications completed to date at the first floor remodel area.
|
FIR13-00661
| INSP-Sprinkler Rough-in/Hydro | 2/14/2014 | 2/18/2014 | 2/17/2014 3:31:38 PM | A | CANC |
|
|
Stefan is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
BLD08-00379
| FIRE-Final Inspection | 2/13/2014 | 2/18/2014 | 2/14/2014 11:47:38 AM | A | PART |
|
|
C/N items completed per contractor. Final walkthrough scheduled 2/18
|