MEC01-00322
| Rough-in | 2/1/2001 | 2/2/2001 | 2/2/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 02/01/2001 at 14:35:56. Contact: ###-####.
|
MEC00-02569
| Final | 2/1/2001 | 2/2/2001 | 2/2/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 02/01/2001 at 15:22:25. Contact: ###-####.
|
MEC00-04096
| Final | 2/1/2001 | 2/2/2001 | 2/2/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 02/01/2001 at 16:03:17. Contact: ###-####.
|
MEC01-00149
| Final | 2/1/2001 | 2/2/2001 | 2/2/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 02/01/2001 at 13:36:09. Contact: ###-####.
|
MEC01-00301
| Final | 2/1/2001 | 2/2/2001 | 2/2/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 02/01/2001 at 13:38:49. Contact: ###-####.
|
BLD01-00143
| BLD-Foundation | 2/1/2001 | 2/2/2001 | 2/2/2001 12:00:00 AM | P | FAIL |
|
|
no work done, no one on site 2/5/2001 9:26:08 AM
|
MEC01-00324
| Pressure Test | 2/2/2001 | 2/2/2001 | 2/2/2001 12:00:00 AM | P | PASS |
|
|
###-####
|
MEC01-00333
| Rough-in | 2/2/2001 | 2/2/2001 | 2/2/2001 12:00:00 AM | P | PASS |
|
|
joe ###-####
|
MEC01-00333
| Pressure Test | 2/2/2001 | 2/2/2001 | 2/2/2001 12:00:00 AM | P | PASS |
|
|
joe ###-####
|
MEC01-00248
| Pressure Test | 2/2/2001 | 2/2/2001 | 2/2/2001 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 02/02/2001 at 11:12:35. Contact: ###-####.
|