Inspections for the day of: Friday, February 2, 2007.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorDave Hannah
TitleBLD-COM/RES INSPECTOR
Phone #794-1967
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD05-01077 BLD-Final2/2/20072/2/20072/5/2007 9:26:58 AMPPART
ok for temp occ c/n to follow needs other trafdes to go perm and ada issuse addressed
BLD06-02053 BLD-Framing/Rough-in2/2/20072/2/20072/5/2007 9:17:08 AMPPART
matt; Phone #: ###-#### Internet Inspection Request from: Victoria Beall rooms not much change
BLD06-02664 BLD-Energy code compliance2/2/20072/2/20072/5/2007 9:03:17 AMPPASS
please come as late in the day as possible. thanks. Gary Phone #: ###-#### ok to cover
BLD06-03111 BLD-Energy code compliance2/2/20072/2/20072/2/2007 1:48:54 PMPPASS
paul; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
BLD05-02304 BLD-Final2/1/20072/2/20072/2/2007 1:36:11 PMAPASS
Scheduled by a contractor via Hello! on 2/1/2007 at 10:44:33 AM. Contact: ###-####. ok for perm occ
BLD06-01521 BLD-Final2/1/20072/2/20072/2/2007 10:44:10 AMAPASS
scott; Phone #: ###-#### Internet Inspection Request from: Victoria Beall ok for perm occ
BLD06-03399 BLD-Foundation2/1/20072/2/20072/2/2007 10:17:14 AMAPART
dean; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
BLD06-00077 BLD-Foundation2/1/20072/2/20072/2/2007 10:16:53 AMAPASS
Scheduled by a contractor via Hello! on 2/1/2007 at 11:17:03 AM. Contact: ###-####.
BLD06-00076 BLD-Footing2/1/20072/2/20072/2/2007 10:16:31 AMAPASS
Scheduled by a contractor via Hello! on 2/1/2007 at 11:14:38 AM. Contact: ###-####.
BLD06-02664 BLD-Framing/Rough-in2/1/20072/2/20072/2/2007 9:45:37 AMAPASS
gary; Phone #: ###-#### Internet Inspection Request from: Victoria Beall ok to insulate
BLD06-02716 BLD-Final2/1/20072/2/20072/2/2007 12:00:00 AMPCANC
Scheduled by a contractor via Hello! on 2/1/2007 at 10:57:17 AM. Contact: ###-####.