Inspections for the day of: Monday, February 2, 2009.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR08-00716 FIR-Aging Inspection2/2/20092/2/20092/5/2009 3:46:21 PM DONE
Work is in progress.
BLD08-02580 FIRE-Final Inspection2/2/20092/2/20092/2/2009 4:04:34 PMPPASS
Life safety passed.
BLD08-01652 FIRE-Final Inspection1/30/20092/2/20092/2/2009 3:02:11 PMAPASS
Life safety passed. The storage racks that exceed 8'-0" in height have been removed as well as the aerosols and solvents.
FIR08-00636 INSP-Alarm Testing1/30/20092/2/20092/2/2009 2:57:56 PMAPASS
Permit finaled. Storage was below 20'-0" at this time. Owner has been notified by the sprinkler contractor that 18" minimum clearance is required from the top of the storage to the sprinkler heads.
BLD07-01278 FIRE-Final Inspection1/30/20092/2/20092/2/2009 2:55:03 PMAPASS
Life safety passed.
FIR08-00772 INSP-Final Inspection1/29/20092/2/20092/2/2009 2:53:48 PMAFAIL
Provide hydro testing per NFPA 13 and 25. Provide data sheets for the newly installed valve on the backflow preventor. Provide as-builts.
BLD06-02722 FIRE-Final Inspection1/30/20092/2/20092/2/2009 11:52:30 AMAPASS
Life safety passed.
BLD08-02541 FIRE-Final Inspection1/30/20092/2/20092/2/2009 10:33:53 AMAPASS
Life safety passed