FIR14-00683
| INSP-Sprinkler Rough-in | 2/2/2015 | 2/2/2015 | 2/2/2015 5:03:18 PM | P | PART |
|
|
Rough-in at portions of the dry and wet systems only.
|
FIR14-00430
| INSP-Sprinkler Rough-in | 1/30/2015 | 2/2/2015 | 2/2/2015 4:02:30 PM | P | PART |
|
|
Inspection intended for project related FIR14-00531 - Tower 2 5th floor living units and common corridor rough in.
|
FIR14-00801
| INSP-Sprinkler Rough-in | 1/30/2015 | 2/2/2015 | 2/2/2015 2:49:32 PM | A | NR |
|
|
Missing approved plans on site. Need to verify cold cavity protection at riser transitions to upper ceiling levels.
|
BLD14-03534
| FIRE-Conference | 2/2/2015 | 2/2/2015 | 2/2/2015 1:25:32 PM | A | DONE |
|
|
On site conference with contractor regarding EM lighting locations, premise identification, FD key box, fire extinguishers, and plan review annotations for door hardware and exit signs.
|
FIR14-00517
| INSP-Final Inspection | 1/30/2015 | 2/2/2015 | 2/2/2015 1:19:45 PM | A | PEND |
|
|
Discussed plan modification and date reviewed, project schedule and RTU installations.
|
BLD14-03615
| FIRE-Final Inspection | 2/2/2015 | 2/2/2015 | 2/2/2015 1:13:50 PM | P | PASS |
|
|
Life safety inspection completed satisfactory. The posted PFE was certified while on site.
|
FIR15-00062
| INSP-Sprinkler Rough-in | 2/2/2015 | 2/2/2015 | 2/2/2015 1:12:06 PM | P | PART |
|
|
Sprinkler system modifications per the scope of work approved for grid ceiling cover. *Note- existing sprinkler piping above the exterior entry may be subject to freeze potential due to the new drop ceiling, sheetrock to deck and lack of HVAC.
|
FIR14-00896
| INSP-Final Inspection | 1/30/2015 | 2/2/2015 | 2/2/2015 1:03:35 PM | A | PART |
|
|
Completed inspection for relocated upright coverage at the warehouse areas due to new and removed walls. Plastic coatings room 205 is not ready for inspection at this time.
|
FIR14-00896
| INSP-Sprinkler Rough-in | 1/30/2015 | 2/2/2015 | 2/2/2015 1:00:31 PM | A | PART |
|
|
Okay to cover overhead work at the front office area grid ceilings.
|