Inspections for the day of: Monday, February 2, 2015.
Number of inspections: 21
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC14-01024 Random Inspection2/2/20152/2/20152/2/2015 4:23:16 PMPPART
WIP. No discharges or trackout down street.

Corrections:
1. Post permit
2. Sweep up street directly in front of home.
ESC14-01045 DOC - Permit Finaled2/2/20152/2/20152/2/2015 4:21:49 PMPPASS
Demo of old house is complete. Now parcel has new house under construcction covered under ESC14-01024. Permit finaled.
ESC14-00413 Site Final2/2/20152/2/20152/2/2015 3:56:02 PMPPASS
Home construction is complete. Yard is landscaped and streets, sidewalk, and gutter have been cleaned. ESC permit conditions satisfied.
ESC14-00413 DOC - Permit Finaled2/2/20152/2/20152/2/2015 3:55:20 PMPPASS
ESC14-00414 Site Final2/2/20152/2/20152/2/2015 3:54:53 PMPPASS
Home construction is complete. Yard is landscaped and streets, sidewalk, and gutter have been cleaned. ESC permit conditions satisfied.
ESC14-00414 DOC - Permit Finaled2/2/20152/2/20152/2/2015 3:51:19 PMPPASS
ESC14-01030 Random Inspection2/2/20152/2/20152/2/2015 3:19:55 PMPPASS
Permit posted with SWPPP and eNOI info. No activity at site at time of inspection. No trackout, discharges or hillside erosion on back bank observed. No corrections required.
ESC14-00499 DOC - Permit Finaled2/2/20152/2/20152/2/2015 3:00:50 PMPPASS
New parking lot has been installed at Campbell Company and has onsite stormwater drainage. No further ESC inspections for this permit, remaining construction activity will be inspected on ESC14-00514
ESC14-00514 General Inspection2/2/20152/2/20152/2/2015 2:57:44 PM PASS
WIP on new building for Campell Co. No trackout offsite to McGregor. MS4 DIs have protection, silt fence perimeter is still install along back of building. No violations observations.
ESC14-01157 BMP Violation1/30/20152/2/20152/2/2015 1:56:17 PMPPASS
Clean up has been completed. Trash and waste building materials were hauled off. Sidewalk, gutter and intersection were cleaned. Big improvement. Site is currently in compliance.
ESC13-00982 Aging Inspection2/2/20152/2/20152/2/2015 1:38:27 PM PASS
WIP. Permit posted. No trackout or muddy runoff leaving site. Last 2 Tahoe homes on Honeycomb will be ready for final next general inspection.
ESC13-00691 Aging Inspection2/2/20152/2/20152/2/2015 1:34:00 PM PASS
ESC14-00899 BMP Violation2/2/20152/2/20152/2/2015 1:33:03 PMPFAIL
Muddy runoff from site that has dirty sidewalk and unfinished driveway is flowing to MS4 DI on State Street and Pierce.

Immediate CN issued to Syringa to install DI protection/witches had filter this afternoon and clean up mud in gutter as much as possible.
ESC13-01208 Aging Inspection2/2/20152/2/20152/2/2015 11:48:20 AM PASS
Homeowner RP project is ongoing but all disturbed area around new detached garage is stabilized/landscaped. Driveway has been poured. No MS4 in area, no issues at site. No further ESC inspections needed. Permit finaled.
ESC13-01208 DOC - Permit Finaled2/2/20152/2/20152/2/2015 11:46:46 AMPPASS
ESC13-01159 General Inspection2/2/20152/2/20152/2/2015 11:23:24 AM PASS
No subdivision development activity. BMPs installed including inlet protection and silt fence with buffer along creek. Two SFH projects have started by CBH.

No trackout outside of sub and stormwater is contained onsite.
ESC14-00774 General Inspection2/2/20152/2/20152/2/2015 10:41:52 AM PASS
Warehouse walls have been erected. Site is flat and is staying well within designated area of disturbance. Construction entrance installed, no significant trackout. Approved.
ESC14-00501 DOC - Permit Finaled2/2/20152/2/20152/2/2015 10:19:22 AMPPASS
Carport complete. Surrounding darking lot paved/stabilzed. Associated 4 plex still in progress - see ESC14-00500
ESC14-00501 General Inspection2/2/20152/2/20152/2/2015 10:17:33 AM PASS
ESC14-00500 General Inspection2/2/20152/2/20152/2/2015 10:17:06 AM PASS
WIP. Frame is up for Aberdeen 4 plex. Some loose dirt/mud in parking lot, but no trackout or muddy runoff to streets and gutters. Streets and parking lanes were swept last week per request. No corrections at this time.
ESC14-00423 General Inspection2/2/20152/2/20152/2/2015 9:33:31 AM PASS
Hillside remodel in progress. BLD on hold. No ESC violations, earthwork complete and ongoing work is inside the home within landscaped/stabilized yard.