MEC01-00451
| Final | 2/16/2001 | 2/20/2001 | 2/20/2001 12:00:00 AM | A | NR |
|
|
need dryer make up air, and comb. air for waterheater, and extend p/t drain line to outdoors 2/20/2001 10:56:57 AM
|
BLD00-01659
| BLD-Final | 2/16/2001 | 2/20/2001 | 2/20/2001 12:00:00 AM | A | PASS |
|
|
corrections done, c/c#19850 2/20/2001 11:18:28 AM
|
MEC01-00479
| Rough-in | 2/16/2001 | 2/20/2001 | 2/20/2001 12:00:00 AM | A | CANC |
|
|
couldn't find address or any work 2/20/2001 12:34:53 PM
|
BLD01-00367
| BLD-Foundation | 2/16/2001 | 2/20/2001 | 2/20/2001 12:00:00 AM | A | CANC |
|
|
called in wrong inspection 2/20/2001 11:24:18 AM
|
MEC00-04338
| Rough-in | 2/19/2001 | 2/20/2001 | 2/20/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 02/19/2001 at 13:40:09. Contact: ###-####.
|
BLD01-00235
| BLD-Footing | 2/19/2001 | 2/20/2001 | 2/20/2001 12:00:00 AM | A | FAIL |
|
|
poured at arrival, basement and ground level footings, no one on site or plans. pumper truck just driving off. 2/20/2001 12:04:23 PM
|
BLD00-03484
| BLD-Footing | 2/20/2001 | 2/20/2001 | 2/20/2001 12:00:00 AM | P | PASS |
|
|
###-####
|
BLD00-03616
| BLD-Footing | 2/20/2001 | 2/20/2001 | 2/20/2001 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 02/20/2001 at 08:52:05. Contact: ###-####.
|
BLD00-03618
| BLD-Footing | 2/20/2001 | 2/20/2001 | 2/20/2001 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 02/20/2001 at 08:53:06. Contact: ###-####.
|
BLD00-01175
| BLD-Final | 2/20/2001 | 2/20/2001 | 2/20/2001 12:00:00 AM | P | NR |
|
|
no electrical final 2/20/2001 2:59:03 PM
|
MEC00-04353
| Rough-in | 2/20/2001 | 2/20/2001 | 2/20/2001 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 02/20/2001 at 11:25:08. Contact: ###-####.
|
BLD01-00235
| BLD-Conference | 2/20/2001 | 2/20/2001 | 2/20/2001 12:00:00 AM | P | PASS |
|
|
Added by Inspector: 350 On 2/20/2001 12:34:19 PM went back to meet builder to go over plans, ftns and setbacks as per plans
|
BLD00-02561
| BLD-Energy code compliance | 2/19/2001 | 2/20/2001 | 2/20/2001 12:00:00 AM | P | PASS |
|
|
corrections fixed, insulation ok 2/20/2001 2:16:26 PM
|