BLD15-00045
| FIRE-Final Inspection | 2/20/2015 | 2/20/2015 | 2/20/2015 2:07:06 PM | P | PASS |
|
|
life safety passed
|
BLD14-03475
| FIRE-Final Inspection | 2/20/2015 | 2/20/2015 | 2/20/2015 2:06:46 PM | P | FAIL |
|
|
See the city approved plans for locations where there are door hardware issues.
|
FIR14-00788
| INSP-Sprinkler Rough-in/Hydro | 2/19/2015 | 2/20/2015 | 2/20/2015 2:02:15 PM | P | PASS |
|
|
Underground hydo test failed
|
FIR15-00012
| INSP-Sprinkler Rough-in | 2/20/2015 | 2/20/2015 | 2/20/2015 12:59:42 PM | P | PASS |
|
|
Remaining piping is ok to cover
|
FIR14-00588
| INSP-Final Inspection | 2/19/2015 | 2/20/2015 | 2/20/2015 12:58:47 PM | P | PASS |
|
|
Permit finaled. Bell added and tested
|
FIR14-00818
| INSP-Sprinkler Rough-in | 2/19/2015 | 2/20/2015 | 2/20/2015 10:17:46 AM | A | PASS |
|
|
forward flush passed
|