FIR11-00431
| INSP-Sprinkler Rough-in/Hydro | 2/20/2012 | 2/21/2012 | 2/22/2012 6:24:21 PM | P | PART |
|
|
Reinspection items at system 2 mechanical include added heads at several locations-6 areas, approx 14 ssu- some in the calc area, rough-in at link 100A okayed, ft2 at corridor 100R not to exceed 130 after pendents are cut in, corrections at nonclean link and TEM labs are incomplete, dock 100C and vestibule 100D no change.
|
FIR11-00301
| INSP-Sprinkler Rough-in/Hydro | 2/20/2012 | 2/21/2012 | 2/22/2012 6:02:10 PM | A | PART |
|
|
System 8 sub fab reinspection items include spacing at the temporary wall is 7'-6", four obstructed uprights adjacent to temporary unistrut trapeeze members, added outlet for chemical cabinets not shown on plans, missing potter air vent per drawings, added vestibules 000B and 002B including fire protection are not included on plans, sheetrock soffit enclosure at the new catwalk creates obstructions in three areas, need to add coverage under newly extended ductwork over 4', missing intermediate hangers under both stairways. Noted overspaced uprights under ductwork system 8 mechanical. Previous c/n items at some areas have been completed. Also noted quantities of sodium hypochlorite, sulfuric acid, process water, DI and IW located within the building.
|
FIR11-00035
| INSP-Sprinkler Rough-in/Hydro | 2/21/2012 | 2/21/2012 | 2/22/2012 4:46:55 PM | P | PASS |
|
|
Fire alarm testing completed satisfactory.
|
BLD11-02990
| FIRE-Conference | 2/21/2012 | 2/21/2012 | 2/22/2012 4:45:25 PM | P | DONE |
|
|
Completed EM light testing, noted two non-functional lights and one exit sign. Walkthrough completed for fire sprinkler coverage. PFE's okay.
|
FIR12-00027
| INSP-Final Inspection | 2/21/2012 | 2/21/2012 | 2/22/2012 4:40:45 PM | P | PASS |
|
|
Fire alarm permit finaled.
|
FIR11-00653
| INSP-Final Inspection | 2/21/2012 | 2/21/2012 | 2/22/2012 4:34:00 PM | P | PASS |
|
|
Fire alarm permit finaled.
|
FIR09-00375
| FIR-Aging Inspection | 2/21/2012 | 2/21/2012 | 2/21/2012 12:58:38 PM | | DONE |
|
|
Contractor to schedule final for 2/23/12 PM
|
BLD12-00268
| FIRE-Final Inspection | 2/17/2012 | 2/21/2012 | 2/21/2012 12:41:19 PM | A | FAIL |
|
|
Remove manual thumbturn at the main entry, post "door to remain...." signage per plan review notes.
|
FIR12-00032
| INSP-Sprinkler Rough-in | 2/17/2012 | 2/21/2012 | 2/21/2012 12:39:32 PM | A | PART |
|
|
Overhead work at the sheetrock and grid ceilings in the tenant remodel okayed for cover.
|
FIR12-00030
| INSP-Sprinkler Rough-in | 2/17/2012 | 2/21/2012 | 2/21/2012 12:38:11 PM | A | PART |
|
|
Overhead install at the break and work rooms only approved for cover as marked and dated on stamped plans.
|
FIR10-00550
| INSP-Final Inspection | 2/16/2012 | 2/21/2012 | 2/21/2012 12:36:42 PM | A | PASS |
|
|
Noted corrections verified for completion. Fire alarm permit finaled.
|
FIR12-00027
| INSP-Alarm Testing | 2/20/2012 | 2/21/2012 | 2/21/2012 12:35:32 PM | A | PASS |
|
|
Scope of fire alarm work completed satisfactory. Inspection passed.
|