BLD19-00464
| FIRE-Final Inspection | 2/21/2019 | 2/21/2019 | 2/21/2019 2:27:08 PM | P | PASS |
|
|
life safety passed
Call to meet // Chris Phone #: ###-####
|
NAF18-00138
| INSP-Final | 2/20/2019 | 2/21/2019 | 2/21/2019 1:34:51 PM | P | PART |
|
|
A temporary for life safety is ok with Boise Fire approval until the fire sprinkler is added at the base of the stairs and a possible riser monitoring system is installed. Call prior to going Phone #: 2082834604 >> Inspection requested via mobile web by Dave
|
FIR19-00056
| INSP-Final Inspection | 2/21/2019 | 2/21/2019 | 2/21/2019 12:21:40 PM | P | PASS |
|
|
Permit finaled
Raul Phone #: ###-####
|
FIR19-00058
| INSP-Final Inspection | 2/21/2019 | 2/21/2019 | 2/21/2019 10:53:53 AM | P | FAIL |
|
|
Retried trip time on the dry pipe valve and it is at 2:00 minutes this time
|
FIR19-00058
| INSP-Final Inspection | 2/20/2019 | 2/21/2019 | 2/21/2019 10:53:12 AM | A | FAIL |
|
|
The sprinkler head under the duct work is passed but the dry system trip time failed. It was 1:47 minutes. Raul Phone #: ###-####
|
FIR18-00429
| INSP-Final Inspection | 2/20/2019 | 2/21/2019 | 2/21/2019 10:36:33 AM | A | FAIL |
|
|
Two pendant heads are overspaced off of the clean room wall. They need to be within 4'5" of the wall
Roy Phone #: ###-####
|
NAF18-00110
| INSP-Conference | 2/20/2019 | 2/21/2019 | 2/21/2019 8:42:53 AM | A | DONE |
|
|
I went over the life safety notes with Bruce and discussed the paint booth installation as addressed on the review comments. Call prior to going Phone #: 2086065557 >> Inspection requested via mobile web by Bruce
|
NAF19-00015
| INSP-Sprinkler Rough-in | 2/20/2019 | 2/21/2019 | 2/21/2019 8:29:46 AM | A | PASS |
|
|
Rough-in passed. Piping can be covered.
Call prior to going Phone #: 2083910988 >> Inspection requested via mobile web by Anthony Minichiello
|