PLM02-00343
| Groundwork | 2/21/2002 | 2/22/2002 | 2/22/2002 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 02/21/2002 at 15:58:21. Contact: ###-####. 3 rd stubs north main level and a 4" sewer extention east to west center into ceiling of di room... also retest failed on dlb cont from chem storage rooms, interior pipoing shattered 48" from south end, repair pending 2/22/2002 11:35:14 AM
|
PLM01-03602
| Final | 2/21/2002 | 2/22/2002 | 2/22/2002 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 02/21/2002 at 17:00:48. Contact: ###-####. airgap t&p drain in basement, traps are to be the same size as the trap arm serving them. 2/22/2002 2:16:39 PM
|
PLM02-00392
| Water and/or Sewer | 2/22/2002 | 2/22/2002 | 2/22/2002 12:00:00 AM | A | PART |
|
|
Added by Inspector: 330 On 2/22/2002 11:56:36 AM sewer test ok covered under foundation but apears to be 4" to within the building
|