ESC15-00857
| Conference | 2/22/2016 | 2/22/2016 | 2/23/2016 3:26:58 PM | P | DONE |
|
|
Contractor in process of making corrections at site. Approved to install rock constuction entrance at end of Arrow Villa. Required 2-3 angular rock. Inspect BMP and work that occured at bottom of subdivision near Stewart Gulch park.
Rock now onsite. No other activity.
|
ESC15-00504
| General Inspection | 2/16/2016 | 2/22/2016 | 2/23/2016 10:48:39 AM | A | PASS |
|
|
No significant trackout onto Gary. No fugitive dust. WIP on Kensington complex.
|
ESC15-00453
| General Inspection | 2/22/2016 | 2/22/2016 | 2/23/2016 8:51:43 AM | | PASS |
|
|
|
ESC15-00541
| General Inspection | 2/16/2016 | 2/22/2016 | 2/22/2016 4:37:36 PM | A | PASS |
|
|
|
ESC13-00524
| General Inspection | 2/22/2016 | 2/22/2016 | 2/22/2016 4:37:20 PM | | PASS |
|
|
|
ESC14-00572
| General Inspection | 2/22/2016 | 2/22/2016 | 2/22/2016 3:26:16 PM | | CANC |
|
|
|
ESC14-01019
| Aging Inspection | 2/22/2016 | 2/22/2016 | 2/22/2016 3:26:06 PM | | PASS |
|
|
|
ESC14-01020
| Aging Inspection | 2/22/2016 | 2/22/2016 | 2/22/2016 3:25:50 PM | | PASS |
|
|
|
ESC13-00443
| Aging Inspection | 2/22/2016 | 2/22/2016 | 2/22/2016 3:24:57 PM | | PASS |
|
|
|
ESC15-01620
| Site Preparation | 2/18/2016 | 2/22/2016 | 2/22/2016 1:43:58 PM | A | PASS |
|
|
Michael Phone #: ###-####
New building in previously constructed commercial area at Union Square. BMPs include stabilized entrance/staging area, DI filter bags on private and MS4 drains, and RP stated new washout will be installed this week for the foundation work.
Approved.
|
ESC15-00035
| General Inspection | 2/22/2016 | 2/22/2016 | 2/22/2016 10:15:11 AM | | PASS |
|
|
|
ESC16-00110
| Site Preparation | 2/22/2016 | 2/22/2016 | 2/22/2016 10:14:05 AM | P | PART |
|
|
Clint Phone #: ###-####
Permit sign posted. Exisiting projects are clean with streets having been swept. Approved for excavation.
Correction: - Tahoe to install new designated washout on Ghost Bar for the new phase with SFHs just starting on Ghost Bar and Boven.
Note: request to require Brundage Bone to provided a drip pan, tarp, or card board to contain oils from pump trucks.
|
ESC15-00556
| General Inspection | 2/16/2016 | 2/22/2016 | 2/22/2016 10:05:29 AM | P | PASS |
|
|
No subdivision work occuring at this time. Site has perimeter sediment controls around open lots, DI bags; and road improvments along Highland Valley Road that have prevented illegal trespass and trackout.
No corrections issued at this time.
|
ESC16-00040
| Site Preparation | 2/19/2016 | 2/22/2016 | 2/22/2016 9:46:59 AM | A | PASS |
|
|
Paul Phone #: ###-####
Belmar BMPs installed, includes designated lined washouts and DI protection on the subdivision inlets. Regular housekeeping and sweep up required weekly. Permit sign posted.
Paul for Tahoe just got certified as an RP and will be a contact for Belmar projects.
|
ESC16-00041
| Site Preparation | 2/19/2016 | 2/22/2016 | 2/22/2016 9:46:42 AM | A | PASS |
|
|
Paul Phone #: ###-####
Belmar BMPs installed, includes designated lined washouts and DI protection on the subdivision inlets. Regular housekeeping and sweep up required weekly. Permit sign posted.
Paul for Tahoe just got certified as an RP and will be a contact for Belmar projects.
|
ESC15-00853
| General Inspection | 2/22/2016 | 2/22/2016 | 2/22/2016 9:34:46 AM | | PASS |
|
|
WIP on retaining wall for townhome subdivision. Construction entrance installed within site at border of existing concrete and loading area. Wattles weighed secured around stockpile area at east end of project. Permits posted inside old nursery building window.
No trackout, no discharges, no other violations observed. Approved.
|
ESC15-01139
| Site Preparation | 2/19/2016 | 2/22/2016 | 2/22/2016 9:07:14 AM | A | PASS |
|
|
Dean Phone #: ###-####
Permit sign(s) posted. Parcel designated by construction fencing to prohibit driving off lot in areas other than the existing paved entrance being used for trackout prevention. Outpak concrete washout kit, trash container, and porta pot located in approved location.
RP is the builder who is on site for all phases of construction. No inlet control needed on streets due ACHD work on the HIll Road and 36th Street roundabout.
Approved for construction.
|
ESC15-01140
| Site Preparation | 2/19/2016 | 2/22/2016 | 2/22/2016 9:06:54 AM | A | PASS |
|
|
Dean Phone #: ###-####
Permit sign(s) posted. Parcel designated by construction fencing to prohibit driving off lot in areas other than the existing paved entrance being used for trackout prevention. Outpak concrete washout kit, trash container, and porta pot located in approved location.
RP is the builder who is on site for all phases of construction. No inlet control needed on streets due ACHD work on the HIll Road and 36th Street roundabout.
Approved for construction.
|