Inspections for the day of: Wednesday, February 23, 2005.
Number of inspections: 6
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR04-00760 INSP-Final Inspection2/22/20052/23/20052/23/2005 12:00:00 AMAFAIL
Replace the painted sprinkler heads 2/23/2005 10:50:00 AM
BLD04-02362 FIRE-Final Inspection2/22/20052/23/20052/23/2005 12:00:00 AMACANC
Duplicate inspection. Finaled 2/22/2005 by 430 2/22/2005 12:41:14 PM
FIR04-00811 INSP-Sprinkler Rough-in/Hydro2/22/20052/23/20052/23/2005 12:00:00 AMPPART
basement hydro test passed. Could not do a rough-in inspection due to plans not matching installation. I spoke to Gerald at Treasure Valley about this. 2/23/2005 2:47:38 PM
FIR05-00037 INSP-Sprinkler Rough-in/Hydro2/23/20052/23/20052/23/2005 12:00:00 AMPPART
With Bill Alexander's permission the remodeled restroom fire sprinklers appear ok. Resubmittals will be required before final will be given. 2/24/2005 9:53:07 AM
FIR04-00666 INSP-Sprinkler Rough-in/Hydro2/23/20052/23/20052/23/2005 12:00:00 AMPPART
Second floor tenting is ok. Second floor piping is ok to cover. Rough-in on first floor center failed. Some upright heads need relocated. Brian will make adjustments. 2/23/2005 4:35:48 PM
FIR05-00078 INSP-Final Inspection2/23/20052/23/20052/23/2005 12:00:00 AMPPART
Sprinkler rough-in passed. Will final when all ceiling tile at heads is installed. 2/23/2005 2:50:45 PM