FIR09-00135
| INSP-Sprinkler Rough-in/Hydro | 2/23/2009 | 2/23/2009 | 2/23/2009 5:12:38 PM | P | PASS |
|
|
Ok to cover two sprinklers in a soffit area.
|
FIR08-00855
| INSP-Sprinkler Rough-in | 2/23/2009 | 2/23/2009 | 2/23/2009 5:11:37 PM | P | FAIL |
|
|
Resubmittal of drawings required. Drawings do not match installation. Antifreeze system was installed instead of the dry system that was shown on the plans.
|
FIR08-00018
| INSP-Sprinkler Rough-in/Hydro | 2/23/2009 | 2/23/2009 | 2/23/2009 5:10:04 PM | P | PASS |
|
|
Ok to cover the corridors on the 9th and 11th Floor
|
FIR08-00045
| INSP-Sprinkler Rough-in/Hydro | 2/23/2009 | 2/23/2009 | 2/23/2009 5:09:01 PM | P | PASS |
|
|
Hydro Test Passed for wet and AnitFreeze
|
BLD07-02290
| FIRE-Final Inspection | 2/23/2009 | 2/23/2009 | 2/23/2009 4:09:03 PM | P | FAIL |
|
|
Provide self closing exit doors to the common exit doors and provide the apartment numbers.
|
BLD09-00152
| FIRE-Final Inspection | 2/20/2009 | 2/23/2009 | 2/23/2009 3:00:52 PM | A | PASS |
|
|
life safety passed
|
FIR07-01042
| INSP-Final Inspection | 2/23/2009 | 2/23/2009 | 2/23/2009 2:50:44 PM | P | PASS |
|
|
Permit finaled
|
FIR07-00928
| INSP-Final Inspection | 2/23/2009 | 2/23/2009 | 2/23/2009 2:47:51 PM | P | PASS |
|
|
Permit finaled
|
BLD06-01451
| FIRE-Final Inspection | 2/20/2009 | 2/23/2009 | 2/23/2009 2:46:34 PM | A | FAIL |
|
|
All life safety items except the exit signs, emergency lights and exit discharge lights appear to be ok. The exit signs, emergency lights and exit discharge lights will be tested tomorrow. The project related fire alarm permit still has two issues that need to be addressed prior to a final occupancy.
|
BLD09-00161
| FIRE-Final Inspection | 2/23/2009 | 2/23/2009 | 2/23/2009 12:09:28 PM | P | PASS |
|
|
life safety passed
|
FIR08-00778
| INSP-Sprinkler Rough-in/Hydro | 2/23/2009 | 2/23/2009 | 2/23/2009 11:58:07 AM | A | FAIL |
|
|
The insulation had not been addressed on the second floor mezzanine so the inspection was stopped until all items are addressed. Per the contractor other areas will be ready at the next inspection.
|
BLD09-00185
| FIRE-Final Inspection | 2/20/2009 | 2/23/2009 | 2/23/2009 11:56:44 AM | A | PART |
|
|
A temporary occupancy was given until the fire extinguisher is provided as discussed, the exit signs/emergency lights are provided and the electrical floor recepticles are covered.
|
FIR08-00045
| INSP-Sprinkler Rough-in/Hydro | 2/20/2009 | 2/23/2009 | 2/23/2009 10:22:17 AM | A | FAIL |
|
|
Hydro test was not even started due to the fitter finding a leak.
|