FIR11-00003
| INSP-Final Inspection | 2/23/2011 | 2/23/2011 | 2/24/2011 4:14:36 PM | P | PASS |
|
|
Fire sprinkler permit finaled.
|
FIR11-00072
| INSP-Conference | 2/23/2011 | 2/23/2011 | 2/23/2011 3:05:54 PM | P | DONE |
|
|
On site conference with contractor regarding pull station locations.
|
BLD11-00110
| FIRE-Final Inspection | 2/23/2011 | 2/23/2011 | 2/23/2011 3:04:38 PM | P | PASS |
|
|
Correction notice items field verified for completion. Fire life safety passed.
|
FIR11-00070
| INSP-Final Inspection | 2/23/2011 | 2/23/2011 | 2/23/2011 3:03:17 PM | P | PASS |
|
|
Fire sprinkler permit work passed inspection.
|
FIR10-00514
| INSP-Sprinkler Rough-in | 2/22/2011 | 2/23/2011 | 2/23/2011 12:51:34 PM | A | PART |
|
|
jeff - ###-####
|
FIR11-00059
| INSP-Sprinkler Rough-in | 2/22/2011 | 2/23/2011 | 2/23/2011 12:50:39 PM | A | PART |
|
|
Verified tenting at overhead supply pipe to the med gas room sprinkler head- blow in insulation is not yet installed.
|