BLD16-01757
| FIRE-Final Inspection | 2/23/2018 | 2/23/2018 | 2/23/2018 11:15:42 AM | P | PART |
|
|
A temporary for the life safety is being given to provide access for State Of Idaho certification. If cooking or training is to be started Scott Arellano is to be contacted for approval. For a final sign off I need the delayed egress doors tested, the project related fire alarm permit finaled and the exit discharge lighting issues approved as discussed.
Steve Phone #: ###-####
|
FIR17-00456
| INSP-Sprinkler Rough-in | 2/23/2018 | 2/23/2018 | 2/23/2018 11:00:23 AM | P | PASS |
|
|
Piping rough-in and tenting passed. Piping can be covered.
|
BLD17-03441
| FIRE-Final Inspection | 2/22/2018 | 2/23/2018 | 2/23/2018 10:59:42 AM | A | PASS |
|
|
life safety passed
tim Phone #: ###-####
|
BLD17-01479
| FIRE-Conference | 2/23/2018 | 2/23/2018 | 2/23/2018 10:43:02 AM | P | DONE |
|
|
We discussed life safety requirements. I noted that the wrong remote annunciator had been installed for the duct smoke detector and that the exit discharge light was missing at the west exit door.
Greg Phone #: ###-####
|
BLD17-01956
| FIRE-Final Inspection | 2/22/2018 | 2/23/2018 | 2/23/2018 9:58:42 AM | A | PASS |
|
|
Life safety passed
Greg Phone #: ###-####
|
BLD13-02973
| FIRE-Final Inspection | 2/21/2018 | 2/23/2018 | 2/23/2018 9:49:21 AM | A | FAIL |
|
|
Provide revised city approved plans for deletion of the exit doors, provide evac plans as per note 23, repair the two north corridor exit signs, provide a K class extinguisher in the Kitchen, provide final inspection for the fire alarm permit, provide elecrical covers in the Nursery.
Jessy Phone #: ###-####
|
FIR14-00701
| INSP-Final Inspection | 2/20/2018 | 2/23/2018 | 2/23/2018 9:44:44 AM | A | FAIL |
|
|
The outside electric alarm bell can be silenced from the FACP which is not allowed. All other items appear ok.
Natalie Phone #: ###-####
|
FIR14-00205
| INSP-Final Inspection | 2/20/2018 | 2/23/2018 | 2/23/2018 9:43:44 AM | A | PASS |
|
|
Permit finaled
Contact Leroy Anderson ###-#### 30 Min prior to Final Insp start please Crane Alarm''s - Peter is contact ###-#### they would like to start at 9:30AM unless you can schedule them for earlier.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
FIR18-00110
| INSP-Final Inspection | 2/22/2018 | 2/23/2018 | 2/23/2018 9:23:03 AM | A | PART |
|
|
The rough-in for the work performd/shown on the plans is passed and piping can be covered. However I noted an overspaced pendant just outside of the tenant entry door
Jim Baker is the contact for this inspection. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|