BLD03-02287
| FIRE-Conference | 2/23/2004 | 2/24/2004 | 2/24/2004 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 2/23/2004 at 11:04:03 AM. Contact: ###-####. met with GC about fire extinguisher placement - will two additional at stair doors and the others as shown on plans 2/24/2004 8:52:35 AM
|
BLD03-02953
| FIRE-Final Inspection | 2/23/2004 | 2/24/2004 | 2/24/2004 12:00:00 AM | A | PASS |
|
|
Dennis; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes
|
FIR03-00538
| INSP-Supply line flush | 2/23/2004 | 2/24/2004 | 2/24/2004 12:00:00 AM | A | PASS |
|
|
john; Phone #: ###-#### Internet Inspection Request from: Barbara Moore see UG permit; flush okay - still needs hydro 2/24/2004 8:16:40 AM
|
FIR03-00616
| INSP-Sprinkler Rough-in/Hydro | 2/23/2004 | 2/24/2004 | 2/24/2004 12:00:00 AM | A | PART |
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Annette Moore UG flush only for the relocated building sprinkler system - okay; attempted to forward flow the BFP through the 2 inch drain and the pitot reading was 10 psi - needed 12 psi to obtain the required flow 2/24/2004 10:06:41 AM
|
FIR03-00788
| INSP-Final Inspection | 2/23/2004 | 2/24/2004 | 2/24/2004 12:00:00 AM | A | CANC |
|
|
CLIFF; Phone #: ###-#### Internet Inspection Request from: Darla Downs--cancel per cilff
|
FIR03-00315
| INSP-Final Inspection | 2/23/2004 | 2/24/2004 | 2/24/2004 12:00:00 AM | A | NR |
|
|
CLIFF; Phone #: ###-#### Internet Inspection Request from: Darla Downs rescheduled for 34/1/04 2/24/2004 8:41:10 AM
|
FIR04-00065
| INSP-Sprinkler Rough-in/Hydro | 2/23/2004 | 2/24/2004 | 2/24/2004 12:00:00 AM | A | PASS |
|
|
jim ; Phone #: ###-#### Internet Inspection Request from: Annette Moore R/I okay - per plans 2/24/2004 10:07:42 AM
|
FIR03-00495
| INSP-Supply line flush | 2/24/2004 | 2/24/2004 | 2/24/2004 12:00:00 AM | A | PASS |
|
|
UG flush okay; still needs hydro 2/24/2004 8:17:04 AM
|
FIR03-00538
| INSP-Sprinkler Rough-in | 2/24/2004 | 2/24/2004 | 2/24/2004 12:00:00 AM | P | FAIL |
|
|
heads not installed in two areas; painted heads and heads with tape; SE area, elevator pit, electrical room not completed; no access to SW area; see plans for the above 2/24/2004 2:15:23 PM
|
FIR03-00153
| INSP-Final Inspection | 2/24/2004 | 2/24/2004 | 2/24/2004 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 2/24/2004 at 8:20:12 AM. Contact: ###-####.
|
FIR03-00154
| INSP-Final Inspection | 2/24/2004 | 2/24/2004 | 2/24/2004 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 2/24/2004 at 8:20:35 AM. Contact: ###-####.
|
FIR03-00155
| INSP-Final Inspection | 2/24/2004 | 2/24/2004 | 2/24/2004 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 2/24/2004 at 8:21:01 AM. Contact: ###-####.
|
FIR03-00156
| INSP-Final Inspection | 2/24/2004 | 2/24/2004 | 2/24/2004 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 2/24/2004 at 8:21:49 AM. Contact: ###-####.
|
FIR03-00157
| INSP-Final Inspection | 2/24/2004 | 2/24/2004 | 2/24/2004 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 2/24/2004 at 8:22:15 AM. Contact: ###-####.
|
FIR03-00158
| INSP-Final Inspection | 2/24/2004 | 2/24/2004 | 2/24/2004 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 2/24/2004 at 8:22:52 AM. Contact: ###-####.
|
FIR03-00159
| INSP-Final Inspection | 2/24/2004 | 2/24/2004 | 2/24/2004 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 2/24/2004 at 8:23:26 AM. Contact: ###-####. The access control elevator lobby doors will need to be tested to verify they release on fire alarm; they will not be active until after the acceptance by the inspector; the remote annunciator at the ramp is not listed for out in the elements 2/24/2004 4:29:07 PM
|
FIR03-00067
| INSP-Final Inspection | 2/24/2004 | 2/24/2004 | 2/24/2004 12:00:00 AM | P | PASS |
|
|
We would like a final this PM. Please call prior to arrival.; Phone #: ###-#### Internet Inspection Request from: Trent Bice
|
FIR03-00088
| INSP-Final Inspection | 2/24/2004 | 2/24/2004 | 2/24/2004 12:00:00 AM | P | FAIL |
|
|
We would like a final this PM. Please
call prior to arrival; Phone #: ###-#### Internet Inspection Request from: Trent Bice west courtyard corridor is not completed - need armovers for two drop in soffit 2/24/2004 4:22:35 PM
|
FIR03-00088
| INSP-Final Inspection | 2/24/2004 | 2/24/2004 | 2/24/2004 12:00:00 AM | P | FAIL |
|
|
We would like a final this PM. Please
call prior to arrival; Phone #: ###-#### Internet Inspection Request from: Trent Bice west courtyard corridor is not completed - need armovers for two drop in soffit 2/24/2004 4:22:35 PM
|
FIR03-00115
| INSP-Final Inspection | 2/24/2004 | 2/24/2004 | 2/24/2004 12:00:00 AM | P | PASS |
|
|
We would like a final this PM. Please call prior to arrival.; Phone #: ###-#### Internet Inspection Request from: Trent Bice
|
FIR03-00115
| INSP-Final Inspection | 2/24/2004 | 2/24/2004 | 2/24/2004 12:00:00 AM | P | PASS |
|
|
We would like a final this PM. Please call prior to arrival.; Phone #: ###-#### Internet Inspection Request from: Trent Bice
|
FIR03-00135
| INSP-Final Inspection | 2/24/2004 | 2/24/2004 | 2/24/2004 12:00:00 AM | P | PASS |
|
|
We would like a final this PM. Please
call prior to arrival.; Phone #: ###-#### Internet Inspection Request from: Trent Bice
|
FIR03-00135
| INSP-Final Inspection | 2/24/2004 | 2/24/2004 | 2/24/2004 12:00:00 AM | P | PASS |
|
|
We would like a final this PM. Please
call prior to arrival.; Phone #: ###-#### Internet Inspection Request from: Trent Bice
|
FIR03-00136
| INSP-Final Inspection | 2/24/2004 | 2/24/2004 | 2/24/2004 12:00:00 AM | P | PASS |
|
|
We would like a final this PM. Please
call prior to arrival.; Phone #: ###-#### Internet Inspection Request from: Trent Bice
|
FIR03-00136
| INSP-Final Inspection | 2/24/2004 | 2/24/2004 | 2/24/2004 12:00:00 AM | P | PASS |
|
|
We would like a final this PM. Please
call prior to arrival.; Phone #: ###-#### Internet Inspection Request from: Trent Bice
|
FIR03-00137
| INSP-Final Inspection | 2/24/2004 | 2/24/2004 | 2/24/2004 12:00:00 AM | P | PASS |
|
|
We would like a final this PM. Please
call prior to arrival.; Phone #: ###-#### Internet Inspection Request from: Trent Bice
|
FIR03-00137
| INSP-Final Inspection | 2/24/2004 | 2/24/2004 | 2/24/2004 12:00:00 AM | P | PASS |
|
|
We would like a final this PM. Please
call prior to arrival.; Phone #: ###-#### Internet Inspection Request from: Trent Bice
|
FIR03-00138
| INSP-Final Inspection | 2/24/2004 | 2/24/2004 | 2/24/2004 12:00:00 AM | P | PASS |
|
|
We would like a final this PM. Please call prior to arrival.; Phone #: ###-#### Internet Inspection Request from: Trent Bice
|
FIR03-00138
| INSP-Final Inspection | 2/24/2004 | 2/24/2004 | 2/24/2004 12:00:00 AM | P | PASS |
|
|
We would like a final this PM. Please call prior to arrival.; Phone #: ###-#### Internet Inspection Request from: Trent Bice
|
FIR03-00139
| INSP-Final Inspection | 2/24/2004 | 2/24/2004 | 2/24/2004 12:00:00 AM | P | PASS |
|
|
We would like a final this PM. Please call prior to arrival.; Phone #: ###-#### Internet Inspection Request from: Trent Bice
|
FIR03-00139
| INSP-Final Inspection | 2/24/2004 | 2/24/2004 | 2/24/2004 12:00:00 AM | P | PASS |
|
|
We would like a final this PM. Please call prior to arrival.; Phone #: ###-#### Internet Inspection Request from: Trent Bice
|
BLD03-02875
| FIRE-Final Inspection | 2/24/2004 | 2/24/2004 | 2/24/2004 12:00:00 AM | P | PART |
|
|
mike ; Phone #: ###-#### Internet Inspection Request from: Annette Moore per Dave Miller a temp occupancy has been approved pending installation of the smoke/fire damper and testing of the fire alarm system 2/24/2004 12:41:58 PM
|
BLD04-00277
| FIRE-Final Inspection | 2/24/2004 | 2/24/2004 | 2/24/2004 12:00:00 AM | P | NH |
|
|
###-#### Jenn -- having BLD final this afternoon as well. Left message and will reschedule for 2/25 AM 2/24/2004 4:08:53 PM
|
BLD03-01845
| FIRE-Conference | 2/17/2004 | 2/24/2004 | 2/24/2004 12:00:00 AM | P | PASS |
|
|
follow up for 5 day notice talked to manager of BD foods and he has Sentry Security involved to update the fire alarm panel and Phil Omas will get drawings and submit plans for the permit 2/24/2004 12:39:57 PM
|