BLD06-01451
| FIRE-Final Inspection | 2/23/2009 | 2/24/2009 | 2/25/2009 10:28:55 AM | A | FAIL |
|
|
Life safety items are ok. Just waiting for the fire alarm resubmittals which were required due to changes/additional devices.
|
BLD06-01450
| FIRE-Final Inspection | 2/23/2009 | 2/24/2009 | 2/25/2009 10:28:13 AM | A | FAIL |
|
|
Life safety items are ok. Just waiting for the fire alarm resubmittals which were required due to changes/additional devices.
|
FIR07-01051
| INSP-Sprinkler Rough-in | 2/23/2009 | 2/24/2009 | 2/25/2009 6:57:09 AM | A | DONE |
|
|
The inspection was for the arm over/drops on the second floor. All of the arm over/drops are ok but it appears that a rough-in inspection for the main/branchline piping has not been performed. At this inspection I did not see a computer entry or markings on the plans indicating the inspection. Due to time limitations the fire sprinkler contractor is scheduling another inspection for tomorrow for a job site meeting to discuss this issue. I also found the second floor 2" west main did not have any earthquake bracing and a branchline located in the library had ceiling grid wire attached to it down its entire length.
|
FIR08-00831
| INSP-Sprinkler Rough-in/Hydro | 2/24/2009 | 2/24/2009 | 2/24/2009 5:02:18 PM | P | PASS |
|
|
1st Floor North Corridor Bldg B - Ok to cover 2nd Floor Bldg B Corridor - Ok to Cover
Told the fire protection contractor and general contractor that the same type of insulation arrangement would not be adequate in the rooms since the composite wood joist were deeper. The corridor joist space was almost entirely filled with insulation. In addition, the corridor joist space were much less than the 160^3 defined in NFPA 13
|
BLD08-02394
| FIRE-Final Inspection | 2/23/2009 | 2/24/2009 | 2/24/2009 4:54:04 PM | P | CANC |
|
|
due to time constraints
|
FIR08-00766
| INSP-Sprinkler Rough-in/Hydro | 2/20/2009 | 2/24/2009 | 2/24/2009 1:52:40 PM | P | CANC |
|
|
This is for cover inspection at 12" site feed at jobsite entrance and south center 12" near main bldg. Please call with time frame. Thank you Phone #: ###-#### Internet Inspection Request from: Jeff Packham Inspection cancelled from web by: Jeff Packham
|
FIR08-00752
| INSP-Final Inspection | 2/24/2009 | 2/24/2009 | 2/24/2009 1:48:12 PM | P | PASS |
|
|
permit finaled
|
BLD08-02101
| FIRE-Final Inspection | 2/23/2009 | 2/24/2009 | 2/24/2009 1:47:41 PM | P | PASS |
|
|
life safety passed
|
FIR08-00195
| INSP-Final Inspection | 2/23/2009 | 2/24/2009 | 2/24/2009 1:45:19 PM | P | PASS |
|
|
permit finaled
|
FIR08-00846
| INSP-Final Inspection | 2/23/2009 | 2/24/2009 | 2/24/2009 1:37:23 PM | A | PASS |
|
|
permit finaled
|
FIR08-00018
| INSP-Sprinkler Rough-in/Hydro | 2/24/2009 | 2/24/2009 | 2/24/2009 12:13:13 PM | P | PASS |
|
|
Ok to Cover 11th Floor Condos 1###-#### Condo 1105 will not be sheet rocked at this time. The fire protection is not completed and will need to be inspected at a later date. There are numerous ducts that pose and obstructions problems. Contractor was reminded that NO space is to be used for storage unless the fire protection system is redesigned and resubmitted. Ok to Cover main corridor on 12th Floor
|
FIR08-00382
| INSP-Final Inspection | 2/23/2009 | 2/24/2009 | 2/24/2009 12:08:34 PM | P | FAIL |
|
|
Apparently the city approved plans have been lost. No inspection was performed.
|
FIR07-01032
| INSP-Final Inspection | 2/23/2009 | 2/24/2009 | 2/24/2009 12:07:40 PM | P | PART |
|
|
The sprinkler work is complete in both the first floor and second floor dining areas. An ok to cover was also given for the first floors nurses station. See the city approved plans for the exact area covered with todays date and my signature.
|
BLD07-01846
| FIRE-Final Inspection | 2/23/2009 | 2/24/2009 | 2/24/2009 12:05:47 PM | P | FAIL |
|
|
The project related fire alarm permit needs addressed. There are missing emergency lights in the second floor dining area and one addition light is needed see plan for location. The exit sign infront of the second floor stair access did not operate.
|
BLD08-02225
| FIRE-Conference | 2/23/2009 | 2/24/2009 | 2/24/2009 9:47:40 AM | A | DONE |
|
|
I went over the life safety requirements/plan review notes with the builder.
|
FIR08-00103
| INSP-Alarm Testing | 2/24/2009 | 2/24/2009 | 2/24/2009 12:00:00 AM | P | DONE |
|
|
TRASH ROOM SMOKE DETECTOR Phone #: ###-#### Internet Inspection Request from: Robert Gobler
|