Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD09-00887 FIRE-Conference2/24/20102/24/20102/26/2010 5:10:42 PMPDONE
On site meeting with project architect regarding IFC sec. 906 and IDAPA amendments.
BLD09-02291 FIRE-Conference2/24/20102/24/20102/24/2010 4:23:28 PMPDONE
Regarding IFC 2006 sec. 1008.1.3.4 criteria for access controlled egress doors items #1 thru 6.
FIR09-00642 INSP-Sprinkler Rough-in/Hydro2/24/20102/24/20102/24/2010 4:18:26 PMPPART
Overhead hydrostatic testing for the new cooler area at the SE corner of the building completed satisfactory after repairs made while on site, noted insufficient seismic clearance at the main through the west wall- contractor to provide flex couplings spaced per NFPA 13 as discussed at this location.
BLD09-00518 FIRE-Conference2/23/20102/24/20102/24/2010 4:12:29 PMADONE
On site visit regarding fire dept. access requirements and conditions outlined per code review notes including item #5.
FIR09-00516 INSP-Final Inspection2/24/20102/24/20102/24/2010 11:37:40 AMAPASS
Correction items verified for completion, fire alarm testing passed, permit work approved for final status, contractor to post map at the panel as discussed.
BLD10-00249 FIRE-Final Inspection2/23/20102/24/20102/24/2010 11:35:05 AMAPASS
Correction notice items are finished, fire life safety passed.
BLD09-00887 FIRE-Final Inspection2/24/20102/24/20102/24/2010 11:34:13 AMPCANC
Incorrect inspection type, not intended for final.