BLD10-02939
| FIRE-Conference | 2/24/2011 | 2/24/2011 | 2/24/2011 4:14:09 PM | P | DONE |
|
|
Regarding project related fire alarm work.
|
FIR10-00634
| INSP-Final Inspection | 2/23/2011 | 2/24/2011 | 2/24/2011 4:13:29 PM | P | PASS |
|
|
Correction items verified, plan modification resubmital okayed. Final inspection passed.
|
FIR11-00042
| INSP-Sprinkler Rough-in | 2/23/2011 | 2/24/2011 | 2/24/2011 4:12:47 PM | A | PART |
|
|
Correction items finished. Okay to cover overhead fire sprinkler work.
|
FIR11-00046
| INSP-Final Inspection | 2/23/2011 | 2/24/2011 | 2/24/2011 4:10:28 PM | P | PART |
|
|
Fire alarm work passed functional testing, final pending correct size sample tube/installation at the duct detector.
|
BLD10-00043
| FIRE-Final Inspection | 2/24/2011 | 2/24/2011 | 2/24/2011 4:06:51 PM | A | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by phil doble
|