Inspections for the day of: Thursday, February 24, 2011.
Number of inspections: 16
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMike Jordan
TitleBLD-COM/RES INSPECTOR
Phone #794-9473
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD11-00019 BLD-Final2/24/20112/24/20112/24/2011 3:04:31 PMPDONE
Phone #: ###-#### >> Inspection requested via web by Robert Hamlin
BLD11-00019 DOC - Permit Finaled2/24/20112/24/20112/24/2011 3:04:16 PMPPASS
BLD11-00020 BLD-Final2/24/20112/24/20112/24/2011 3:04:03 PMPDONE
Phone #: ###-#### >> Inspection requested via web by Robert Hamlin
BLD11-00020 DOC - Permit Finaled2/24/20112/24/20112/24/2011 3:03:42 PMPPASS
ESC11-00006 Site Final2/24/20112/24/20112/24/2011 2:57:51 PMPDONE
ESC11-00006 DOC - Permit Finaled2/24/20112/24/20112/24/2011 2:56:39 PMPPASS
BLD11-00053 BLD-Final2/23/20112/24/20112/24/2011 2:33:43 PMPPASS
ben Phone #: ###-####. ok for perm. occ.
BLD10-00862 BLD-Framing/Rough-in2/24/20112/24/20112/24/2011 1:29:35 PMPPASS
MATT Phone #: ###-####. Interior steel stud wall. Noted no rough ins in this wall.
BLD10-01256 BLD-Framing/Rough-in2/23/20112/24/20112/24/2011 12:07:56 PMAPASS
Mike, I need you to inspect the roof sheeting on the addition and look at a existing handrail. Phone #: ###-#### >> Inspection requested via web by Gary Simon. Inspected roof diaphragm attatchment at new entryway, also inspected exisiting handrail, will bring to code.
BLD11-00265 BLD-Other2/24/20112/24/20112/24/2011 12:05:33 PMAPASS
Attachment of 5/8 type x rock for 1hr. ceiling asembly and 1hr. firewall ok.
BLD10-02915 BLD-Other2/23/20112/24/20112/24/2011 11:44:47 AMAPASS
drywall nail inspection 2nd layer//cameron Phone #: ###-####. face layer of 5/8 type x rock for 1hr. ceiling and 1hr. firewall.
ESC10-00917 Random Inspection2/24/20112/24/20112/24/2011 10:55:51 AMAPASS
MIS11-00042 BLD-Conference2/23/20112/24/20112/24/2011 10:43:43 AMAFAIL
Investigate conversion issue Correction Notice to obtain a Certificate of Occupancy. A conversion has taken place, noted no occupants at this time. Appeasrs that exterior work to building has been done as well as an asphalt parkinglot. Could not asses if any interior work was done at this time. A correction notice has been issued stating to submit plans to plan reveiw to obtain all required permits and approvals and to get all required inspections to obtain a certificate of occupancy.
MIS10-00082 BLD-Conference2/16/20112/24/20112/24/2011 10:40:11 AMADONE
A 25 day notice has been issued. After speaking to tenants, noted that they have submited plans to plan review for approval.
GCB10-00085 GCB-Energy2/23/20112/24/20112/24/2011 9:39:02 AMAPASS
EnergyKelly @ ###-####
GCB10-00085 GCB-Framing2/23/20112/24/20112/24/2011 9:38:20 AMAPASS
FramingKelly @ ###-####. All framing issues have been resolved. Framing ok.