ESC12-01066
| Tracking Control | 2/24/2014 | 2/24/2014 | 2/24/2014 2:20:08 PM | P | FAIL |
|
|
Verbal warning issued via phone. Two corrections:
1. Sweep up track out in gutter from NE construction entrance. 2. Install DI protection on MS4 north of construction entrance.
|
ESC14-00109
| Site Preparation | 2/24/2014 | 2/24/2014 | 2/24/2014 2:01:16 PM | P | PASS |
|
|
Privada Estates - Penn canal site prep.
Meet RP on-site. BMPs installed and discussed current phase of project. Construction will begin starting tomorrow. The construction entrance will be moved back from road due to existing asphalt. Instead of how it is on ESC plan. Approved.
|
ESC12-01127
| General Inspection | 2/24/2014 | 2/24/2014 | 2/24/2014 1:10:13 PM | | PASS |
|
|
House is complete and appears to be occupied. BLD permit is open. Will continue to monitor bank stabilization but may ready for final next inspection.
|
ESC13-00448
| General Inspection | 2/24/2014 | 2/24/2014 | 2/24/2014 1:04:01 PM | | PASS |
|
|
Finaled.
|
ESC13-00448
| DOC - Permit Finaled | 2/24/2014 | 2/24/2014 | 2/24/2014 1:02:12 PM | P | PASS |
|
|
All landsaping installed and stabilization complete. BLD permit open, but ESC conditions have been satisfied. No further inspections required.
|
ESC10-00738
| Aging Inspection | 2/24/2014 | 2/24/2014 | 2/24/2014 12:37:51 PM | | PASS |
|
|
Project still in progress with recent activity on permits. No violations observed.
|
ESC12-01155
| General Inspection | 2/24/2014 | 2/24/2014 | 2/24/2014 11:14:40 AM | | PASS |
|
|
Hillside is still not stabilized. Silt fences installed properly. No track out or sediment from project on Starcrest. Approved.
|
ESC13-01270
| Site Preparation | 2/24/2014 | 2/24/2014 | 2/24/2014 11:04:02 AM | P | PASS |
|
|
austin Phone #: ###-####
Discussed projects with Hunter Homes RP Austin. Work so far has been mostly in compliance considering amount of acitivity. Reminded him to continue BMP maintenance, regular sweeping, and continuing to call in site prep inspections. Approved.
|
ESC13-01241
| Site Preparation | 2/24/2014 | 2/24/2014 | 2/24/2014 10:57:35 AM | P | PASS |
|
|
austin Phone #: ###-####
Permit posted. Alleyways and roads have minimal trackout. Concrete washout on Honeycomb block for Hunter Homes has adequate washout capacity and will be replaced at end of week. Approved.
|
ESC13-01250
| Site Preparation | 2/24/2014 | 2/24/2014 | 2/24/2014 10:53:27 AM | P | PASS |
|
|
austin Phone #: ###-####
Permit posted. Alleyways and roads have minimal trackout. Concrete washout on Honeycomb block for Hunter Homes has adequate washout capacity and will be replaced at end of week. Approved.
|
ESC13-00839
| General Inspection | 2/24/2014 | 2/24/2014 | 2/24/2014 10:30:52 AM | | PASS |
|
|
Homeowner project. Permit is posted. No corrections at this time.
|
ESC13-00364
| General Inspection | 2/24/2014 | 2/24/2014 | 2/24/2014 10:09:59 AM | | PASS |
|
|
Warehouse structure is erected. Work is going on for parking lot. No disturbance outside construction limits/fence and no track out to Federal Way. Approved.
|
ESC12-01001
| Aging Inspection | 2/24/2014 | 2/24/2014 | 2/24/2014 9:54:07 AM | | PASS |
|
|
Finaled.
|
ESC12-01001
| DOC - Permit Finaled | 2/24/2014 | 2/24/2014 | 2/24/2014 9:52:33 AM | P | PASS |
|
|
LNG fueling station complete. ESC conditions satisfied. No further inspections necessary. BLD permits finaled except for rough grading.
|
ESC13-00294
| Aging Inspection | 2/24/2014 | 2/24/2014 | 2/24/2014 9:29:36 AM | | PASS |
|
|
RP/GC on site, mud clods from previous week's track out have been fully cleaned. Coconut fiber mat on DI, and access restricted to dirt lot for contractors. No corrections required.
|
ESC13-00661
| DOC - Permit Finaled | 2/24/2014 | 2/24/2014 | 2/24/2014 9:12:31 AM | P | PASS |
|
|
4 plex is complete and stabilized. Other phases of Aberdeen Place still in progress. ESC conditions satisfied.
|
ESC13-00670
| General Inspection | 2/24/2014 | 2/24/2014 | 2/24/2014 9:06:55 AM | | PASS |
|
|
|
ESC13-00661
| General Inspection | 2/24/2014 | 2/24/2014 | 2/24/2014 8:33:20 AM | | PASS |
|
|
|