ESC14-01199
| BMP Violation | 2/24/2015 | 2/24/2015 | 2/24/2015 3:36:19 PM | P | PEND |
|
|
CBH reportedly on site in Dropzone cleaning streets and improving conditions at site.
Corrections to be checked for tomorrow morning.
|
ESC14-00266
| General Inspection | 2/24/2015 | 2/24/2015 | 2/24/2015 2:31:49 PM | | PASS |
|
|
Project near completion. No trackout or sediment leaving site. Rear perimeter silt fence is in good condition and trenched in. No corrections.
|
ESC14-00526
| General Inspection | 2/24/2015 | 2/24/2015 | 2/24/2015 1:04:09 PM | | PASS |
|
|
WIP. No exposed soils , site is surrounded by pavement with private drainage. No trackout or other issues. Frame for warehouse is up.
|
ESC15-00099
| Site Preparation | 2/23/2015 | 2/24/2015 | 2/24/2015 12:34:23 PM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Braxton Hansen
Site ready for excavation. Mill District Square projects are in compliance. Permit posted.
|
ESC14-00804
| General Inspection | 2/24/2015 | 2/24/2015 | 2/24/2015 12:24:47 PM | | PASS |
|
|
WIP. No trackout to Millet. Just requested that street sweeping occuring weekly on the access road. No discharges or erosion observed, just some loose sediment on driveway/access road.
|
ESC13-00684
| General Inspection | 2/24/2015 | 2/24/2015 | 2/24/2015 12:20:01 PM | | PASS |
|
|
Site perimeter is contained construction related sediment on site. DIs have inlet protection. No runoff from lots observed. No corrections necessary at Antelope Springs.
|
ESC14-00943
| Random Inspection | 2/24/2015 | 2/24/2015 | 2/24/2015 12:05:10 PM | P | PASS |
|
|
Culdesac on Hardrock is clean, no trackout. Permit posted on site. Workers and equipment staying off vegetated areas to preserve existing vegetative buffer.
No hillside erosion or other issues occuring, silt fence has been removed but active grading is already complete. Approved.
|
ESC14-00135
| General Inspection | 2/24/2015 | 2/24/2015 | 2/24/2015 11:40:16 AM | | PASS |
|
|
WIP. Culdesac clean. No sediment running off site. No spills or uncontained trash. No correctoins at this time.
|
ESC14-00614
| General Inspection | 2/24/2015 | 2/24/2015 | 2/24/2015 11:23:39 AM | P | PART |
|
|
Lower section of erosion control blanket is staying in place by being tacked in and grass is starting to grow through fabric in areas. Silt fence below rock wall is trenched in a stopping sediment from moving down hill. Street is clean and trash contained.
Top of erosion control blanket needs to be tacked in and re-installed. Looks like the seeds are not taking in this area either. Should repair during the dry conditions.
Check next inspection for repair.
|
ESC14-01023
| Random Inspection | 2/24/2015 | 2/24/2015 | 2/24/2015 11:21:22 AM | A | PASS |
|
|
WIP. Silt fence in retaining sediment and dirt on site. Side walk clean, construction entrance preventing trackout. DI bag installed at receiving inlet. No wind blown trash issues.
Approved.
|
ESC12-01066
| Site Final | 2/23/2015 | 2/24/2015 | 2/24/2015 9:55:39 AM | A | PART |
|
|
Construction is complete and site is landscaped & stabilized.
Correction request to remove temporary BMPs (drop inlet protection) on MS4 structures. RP Kent stated filter bags will be removed by the end of this week. Also need to remove accumulated sediment in front of filter.
Will check back,
|
ESC14-00644
| Aging Inspection | 2/24/2015 | 2/24/2015 | 2/24/2015 9:30:57 AM | | PASS |
|
|
Addition complete and disturbed area in yard has been stabilized and gutters are free sediment or construction materials.. BLD still open, ESC permit conditions satisfied.
|
ESC14-00644
| DOC - Permit Finaled | 2/24/2015 | 2/24/2015 | 2/24/2015 9:29:36 AM | P | PASS |
|
|
|
ESC14-00284
| General Inspection | 2/24/2015 | 2/24/2015 | 2/24/2015 8:47:03 AM | | PASS |
|
|
Home occupied. Waiting to confirm spring time revegetation. No ESC issues.
|
ESC14-00289
| General Inspection | 2/24/2015 | 2/24/2015 | 2/24/2015 8:40:30 AM | | PASS |
|
|
|