BLD15-02560
| FIRE-Final Inspection | 2/24/2016 | 2/24/2016 | 2/25/2016 10:18:55 AM | P | PASS |
|
|
life safety passed
|
FIR16-00104
| INSP-Sprinkler Rough-in/Hydro | 2/23/2016 | 2/24/2016 | 2/24/2016 3:04:42 PM | P | FAIL |
|
|
Todays inspection was for the east building. Almost all of the underground supply piping has been installed/covered by a contractor that is not Shilo. The portion of previously buried piping that is uncovered measured only 3'-6" below grade. The portion that Shilo has installed is buried at the correct depth. The previously installed piping needs to be dug up and re-installed at a minimum 4'-6" bury depth as per Ordinance and plans. No piping is to be covered at this time.
|
FIR13-00223
| FIR-Aging Inspection | 2/24/2016 | 2/24/2016 | 2/24/2016 2:19:21 PM | P | CANC |
|
|
Rescheduled for tomorrow morning
|
FIR15-00618
| INSP-Final Inspection | 2/23/2016 | 2/24/2016 | 2/24/2016 1:49:02 PM | P | FAIL |
|
|
Will be ok to final when the SImplex permit for the dialer is finaled.
|
FIR15-00513
| INSP-Final Inspection | 2/23/2016 | 2/24/2016 | 2/24/2016 1:41:55 PM | P | PASS |
|
|
Permit finaled
|
FIR16-00032
| INSP-Sprinkler Rough-in/Hydro | 2/24/2016 | 2/24/2016 | 2/24/2016 12:15:17 PM | P | PASS |
|
|
All sprinkler work is complete except for the two tamper switches being connected to the facp
|
BLD15-02562
| FIRE-Final Inspection | 2/24/2016 | 2/24/2016 | 2/24/2016 11:53:41 AM | P | PASS |
|
|
life safety passed
|
BLD15-02559
| FIRE-Final Inspection | 2/24/2016 | 2/24/2016 | 2/24/2016 11:22:36 AM | P | PASS |
|
|
Life safety passed
|
FIR15-00711
| INSP-Final Inspection | 2/24/2016 | 2/24/2016 | 2/24/2016 11:09:46 AM | P | PASS |
|
|
Permit finaled
|
BLD15-02561
| FIRE-Final Inspection | 2/24/2016 | 2/24/2016 | 2/24/2016 11:08:07 AM | P | PASS |
|
|
Life safety passed
|
FIR09-00051
| FIR-Aging Inspection | 2/24/2016 | 2/24/2016 | 2/24/2016 10:43:24 AM | | NR |
|
|
Contractor is out of business and sold accounts to Taylor Brothers.
|
BLD15-02842
| FIRE-Conference | 2/24/2016 | 2/24/2016 | 2/24/2016 8:56:28 AM | A | DONE |
|
|
Dutch and I went over life safety requirements for the north half of the building
|
NAF15-00045
| INSP-Final | 2/23/2016 | 2/24/2016 | 2/24/2016 8:53:03 AM | A | FAIL |
|
|
Project is not ready for final as requested. Project is not ready for rough-in yet. Missing earthquake bracing, missing upright coverage in pockets at the main entry, pipe sizing of riser nipples and starter pieces do not match the approved plans, missing dry sidewall heads in the exterior pockets. I gave the general contractor the ok to cover hard lids as indicated on the plans. Resubmittals are required showing all changes such as piping size changes and the additional fittings used, and additional sprinkler heads.
|