Inspections for the day of: Monday, February 25, 2002.
Number of inspections: 12
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAlan Hauser
TitleMEC-COM/RES INSPECTOR
Phone #794-9453
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MEC02-00481 Rough-in2/22/20022/25/20022/25/2002 12:00:00 AMAFAIL
no cover til gas piping approved, also f/p corrections 2/25/2002 10:29:18 AM
MEC02-00481 Pressure Test2/22/20022/25/20022/25/2002 12:00:00 AMAFAIL
no pressure gage at piping 2/25/2002 10:28:36 AM
MEC02-00466 Rough-in2/22/20022/25/20022/25/2002 12:00:00 AMAPART
Scheduled by a contractor via Hello! on 02/22/2002 at 14:07:38. Contact: ###-####. 2nd flr. main area only, no offices 2/25/2002 10:07:53 AM
MEC02-00339 Rough-in2/22/20022/25/20022/25/2002 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 02/22/2002 at 15:20:55. Contact: ###-####.
MEC02-00339 Pressure Test2/22/20022/25/20022/25/2002 12:00:00 AMAPART
Scheduled by a contractor via Hello! on 02/22/2002 at 15:21:11. Contact: ###-####. pt ok, no pipe sizing 2/25/2002 11:07:09 AM
MEC02-00448 Rough-in2/25/20022/25/20022/25/2002 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 02/25/2002 at 09:13:10. Contact: ###-####.
MEC01-03659 Final2/25/20022/25/20022/25/2002 12:00:00 AMPNR
###-#### JOE
MEC01-02351 Final2/25/20022/25/20022/25/2002 12:00:00 AMPPASS
Scheduled by Inspector: 350 On 2/25/2002 10:40:41 AM
MEC01-03725 Final2/25/20022/25/20022/25/2002 12:00:00 AMPNR
###-#### need electrical finished at range hoods 2/25/2002 1:56:43 PM
MEC01-03687 Final2/25/20022/25/20022/25/2002 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 02/25/2002 at 11:26:10. Contact: ###-####.
MEC02-00554 Pressure Test2/25/20022/25/20022/25/2002 12:00:00 AMPPASS
lock box 3096 ###-####
MEC00-01973 Final2/22/20022/25/20022/25/2002 12:00:00 AMPFAIL
John ###-#### pipe pop off drain from water heater to outdoors 2/25/2002 2:44:30 PM