Inspections for the day of: Tuesday, February 25, 2003.
Number of inspections: 5
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorRick Jackson
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR02-00493 INSP-Sprinkler Rough-in/Hydro2/24/20032/25/20032/25/2003 12:00:00 AMAPART
Scheduled by a contractor via Hello! on 2/24/2003 at 11:54:49 AM. Contact: ###-####. underground okay to cover; will need hydro on UG and FDC; flush required also; okay to cover overhead 2/25/2003 10:56:59 AM
FIR02-00419 INSP-Final Inspection2/24/20032/25/20032/25/2003 12:00:00 AMAPASS
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung will doc final at final inspection 2/25/2003 12:23:40 PM
FIR02-00493 INSP-Sprinkler Rough-in/Hydro2/25/20032/25/20032/25/2003 12:00:00 AMPFAIL
tried hydro - one head has small leak at main entrance - will rehydro 2/25/2003 3:41:26 PM
BLD00-03428 FIRE-Conference2/25/20032/25/20032/25/2003 12:00:00 AMPPART
all dampers checked - one not working on third floor at AHU 6 return; will recheck it at a later date 2/25/2003 3:40:18 PM
FIR02-00256 INSP-Final Inspection2/21/20032/25/20032/25/2003 12:00:00 AMPCANC
Scheduled by a contractor via Hello! on 2/21/2003 at 2:47:18 PM. Contact: ###-####. rescheduled for 2/28 at 3 pm 2/25/2003 12:22:05 PM