Inspections for the day of: Monday, February 25, 2008.
Number of inspections: 5
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD05-00633 FIRE-Conference2/25/20082/25/20082/26/2008 4:16:39 PMPCANC
FIR08-00085 INSP-Sprinkler Rough-in2/25/20082/25/20082/25/2008 4:48:58 PMPPART
Rough-in inspection passed. Plans are being resubmitted as per Ben due to sprinkler heads being changed which is effecting the K factor. Piping in the kitchen wall can be covered. A tenting inspection will be required prior to covering with insulation.
BLD05-03423 FIRE-Final Inspection2/25/20082/25/20082/25/2008 4:24:35 PMPFAIL
There were no approved plans or notes on site. No inspection performed.
FIR08-00070 INSP-Supply line flush2/25/20082/25/20082/25/2008 4:23:41 PMPPASS
The underground flush passed.
FIR07-00987 INSP-Conference2/25/20082/25/20082/25/2008 4:20:42 PMPDONE
Conference was for placement of the Knox Box. As it turned out there is an existing knox box mounted on the right hand side of the gate and per personell with Idaho Power the Knox Box contains card passes for both buildings.