FIR09-00709
| INSP-Conference | 2/24/2010 | 2/25/2010 | 2/26/2010 5:49:58 PM | A | DONE |
|
|
Site visit scheduled 2/26 @ 9:30AM.
|
FIR10-00080
| INSP-Sprinkler Rough-in | 2/25/2010 | 2/25/2010 | 2/26/2010 5:22:26 PM | P | PART |
|
|
Overhead work per the scope of the permit is satisfactory, okayed cover at the drop ceilings. Noted the building is not equipped with a fire alarm panel and lacks fire sprinkler system monitoring.
|
FIR09-00642
| INSP-Sprinkler Rough-in/Hydro | 2/25/2010 | 2/25/2010 | 2/26/2010 5:18:00 PM | P | PART |
|
|
Begin 24 hr air testing of the new dry system piping at the SE cooler area at 50 psig. @ 2:00PM 2/25. Also completed hydrostatic testing of the new antifreeze loop at the north dock.
|
FIR09-00707
| INSP-Sprinkler Rough-in | 2/25/2010 | 2/25/2010 | 2/25/2010 4:03:54 PM | P | PART |
|
|
Antifreeze system piping at the west canopy as marked on approved plan set with todays date and initialed okay for cover, one minor adjustment made while on sie, also okayed insulation fill at perimeter soffits on the new porte cochere.
|
FIR09-00536
| INSP-Sprinkler Rough-in | 2/24/2010 | 2/25/2010 | 2/25/2010 3:42:44 PM | A | PART |
|
|
Begin 24 hr. pneumatic testing of the new dry system at 11:00PM @41psig.
|
BLD09-02227
| FIRE-Conference | 2/24/2010 | 2/25/2010 | 2/25/2010 3:41:09 PM | A | DONE |
|
|
On site conferecne regarding fire sprinkler protection at the relocated radio test room and conditions per IFC 2006 903.3.1.1.1.
|