FIR02-00023
| INSP-Supply line flush | 2/25/2002 | 2/26/2002 | 2/26/2002 12:00:00 AM | A | CANC |
|
|
cancelled by contractor 2/26/2002 7:53:53 AM
|
BLD01-03169
| FIRE-Conference | 2/25/2002 | 2/26/2002 | 2/26/2002 12:00:00 AM | A | DONE |
|
|
Verified rough-in of sprinkler heads above soffits and locations of fire extinguishers. 2/26/2002 10:08:58 AM
|
FIR02-00042
| INSP-Sprinkler Rough-in/Hydro | 2/25/2002 | 2/26/2002 | 2/26/2002 12:00:00 AM | A | FAIL |
|
|
New sprinkler heads along west wall are closer than 6'. They must be relocated 2/26/2002 9:01:12 AM
|
BLD01-02896
| FIRE-Conference | 2/26/2002 | 2/26/2002 | 2/26/2002 12:00:00 AM | A | NR |
|
|
Added by Inspector: 430 On 2/26/2002 9:46:14 AM Stopped at project to check on progress of correction notice. Owner is almost complete with corrections per tenant.
|
BLD01-02628
| FIRE-Final Inspection | 2/26/2002 | 2/26/2002 | 2/26/2002 12:00:00 AM | P | FAIL |
|
|
add fire extinguisher 2/26/2002 12:43:53 PM
|
FIR02-00003
| INSP-Sprinkler Rough-in/Hydro | 2/25/2002 | 2/26/2002 | 2/26/2002 12:00:00 AM | P | FAIL |
|
|
add hangers in north rooms and in corridor 2/26/2002 5:04:43 PM
|
BLD02-00053
| FIRE-Final Inspection | 2/26/2002 | 2/26/2002 | 2/26/2002 12:00:00 AM | P | FAIL |
|
|
provide inspection tag on fire extinguisher and provide approved fire sprinkler drawings 2/26/2002 5:05:22 PM
|