Inspections for the day of: Tuesday, February 26, 2008.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR07-00402 FIR-Aging Inspection2/26/20082/26/20082/26/2008 4:47:31 PM DEFR
Not yet completed for inspection, work in progress.
BLD04-03036 FIRE-Final Inspection2/25/20082/26/20082/26/2008 4:43:15 PMAPASS
Corrections are complete, life safety inspection passed. Noted the elevator fire door needs adjusted for complete closure-to be repaired prior to structural final as discussed.
BLD07-01654 FIRE-Conference2/26/20082/26/20082/26/2008 4:40:16 PMPDONE
On site conference to discuss project phasing affecting fire alarm permit work.
BLD06-00755 FIRE-Final Inspection2/26/20082/26/20082/26/2008 4:37:21 PMPPASS
Fire life safety finaled.
FIR06-00326 INSP-Final Inspection2/26/20082/26/20082/26/2008 3:35:56 PMPPASS
Fire sprinkler permit work finaled.
FIR08-00105 INSP-Final Inspection2/25/20082/26/20082/26/2008 3:35:13 PMAPASS
Corrections are complete, final alarm testing passed per KR site visit, permit finaled.
FIR08-00113 INSP-Sprinkler Rough-in2/25/20082/26/20082/26/2008 3:34:10 PMAPART
Fire sprinkler rough-in is good for cover at the hard lid ceiling areas as red lined on approved plan set.
FIR08-00100 INSP-Final Inspection2/25/20082/26/20082/26/2008 3:32:42 PMAPASS
Fire alarm work passed field inspection per KR, permit finaled.
FIR08-00144 INSP-Sprinkler Rough-in2/25/20082/26/20082/26/2008 3:31:18 PMAPART
Overhead system modifications are approved for cover at the drop ceilings.