Inspections for the day of: Friday, February 26, 2010.
Number of inspections: 6
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD10-00118 FIRE-Final Inspection2/26/20102/26/20102/26/2010 4:02:13 PMPPASS
Life safety passed.
BLD10-00339 FIRE-Final Inspection2/25/20102/26/20102/26/2010 4:01:56 PMPFAIL
Provide building address, mount the first floor fire extinguisher and provide an additional tagged fire extinguisher on the mezzanine.
FIR10-00063 INSP-Final Inspection2/26/20102/26/20102/26/2010 4:01:08 PMPPASS
Permit finaled
FIR10-00050 INSP-Sprinkler Rough-in/Hydro2/24/20102/26/20102/26/2010 4:00:49 PMAPASS
The remaining sprinkler piping can be covered. Permit will be ready to final when the ceiling tile has been installed.
FIR10-00063 INSP-Sprinkler Rough-in2/25/20102/26/20102/26/2010 3:59:52 PMAPASS
The insulation has been repaired and the sprinkler piping can be covered.
BLD10-00173 FIRE-Final Inspection2/25/20102/26/20102/26/2010 11:55:59 AMAPASS
Life safety passed