ESC19-00178
| General Inspection | 2/26/2020 | 2/26/2020 | 2/28/2020 9:35:00 AM | | PASS |
|
|
Site still needs to be landscaped, has revegetation bond.
|
ESC19-00270
| Aging Inspection | 2/26/2020 | 2/26/2020 | 2/27/2020 1:46:48 PM | | PASS |
|
|
Exterior of both home and ADU look completed. Lot is still bare. Mostly clean, one area of paint washout.
|
ESC19-00249
| Aging Inspection | 2/26/2020 | 2/26/2020 | 2/27/2020 10:37:25 AM | | PASS |
|
|
Entire site is gravel covered and clean. Exterior work nearly completed on all buildings. No loose trash, no issues.
|
ESC19-01734
| Site Preparation | 2/26/2020 | 2/26/2020 | 2/26/2020 3:42:29 PM | P | PASS |
|
|
Met with Robert Bruno on site. Has perimeter wattle along bottom, lined washout, and lined entrance. Storing backfill on neighboring parcel, is owner. ] Crew setting forms.
|
ESC17-00018
| General Inspection | 2/26/2020 | 2/26/2020 | 2/26/2020 3:20:10 PM | | PASS |
|
|
All work east of Eckert completed. 1 home framed and under construction to west, 1 home just getting forms delivered to site. Ecopans on site.
|
ESC19-00584
| General Inspection | 2/26/2020 | 2/26/2020 | 2/26/2020 3:11:42 PM | P | PASS |
|
|
Water being discharged is .84 NTU. Still only one well point ready, plans on getting second pumping tomorrow. Will pump into pond retention until clear and add to water leaving site. Some ponding along pipeline fromm leaking seals. Will get repaired, county is concerned about water backing up into storm drain along Warm Springs, will add berm around sewer cap. Hauling material out of west pond to north side of road, has sweeper runnuing and makes sure everything clean end of day. Keeping NTU log on site.
|