ESC07-01463
| Site Final | 2/27/2008 | 2/27/2008 | 2/27/2008 2:58:34 PM | P | PASS |
|
|
site stabilized . Sprayed with a type of hydro seed. PASS CAS#460 ###-####
|
ESC07-01185
| Tracking Control | 2/27/2008 | 2/27/2008 | 2/27/2008 2:27:09 PM | P | PART |
|
|
Tracking coming off of project onto Garfield and Denver. Pat (rp) said a street sweeper will be coming through tonight for clean up. Also recommended expanding construction entrance and having all construction workers to park in the parking lot of the church next store. Will re-inspect the 29th of feb. 08 CAS#460 ###-####
|
ESC07-01279
| Site Preparation | 2/27/2008 | 2/27/2008 | 2/27/2008 2:09:06 PM | P | CANC |
|
|
Installed a sediment barrier (wattle) along the creek area to stop anytype of sediment from going into. CAS#460 ###-####
|
ESC07-01541
| Site Preparation | 2/27/2008 | 2/27/2008 | 2/27/2008 2:04:28 PM | P | PART |
|
|
Site perimeter has a vegitative buffer. Construction entrance installed properly. D.I. Protection installed correctly.
Permit Sign needs to be posted. with proper info. left message with Greg Hartly (###-####) CAS#460 ###-####
|
ESC07-01093
| BMP Violation | 2/27/2008 | 2/27/2008 | 2/27/2008 10:16:29 AM | A | FAIL |
|
|
**Notice of Correction** This is for the Whole Project Area 1.No BMP Perimeter Control 2.Trash Debris around all lots. 3. Sediment tracking on Crawford and onto Mitchell off of all lots. 4.Post Signage on all Lots 5.D.I. maintenance required on d.i.'s on plan Failure to comply with the violation will reult in a Stop work order of entire project. Will re-inspect on Friday the 29th at 12pm. CAS#460 ###-####
|