FIR11-00365
| INSP-Sprinkler Rough-in/Hydro | 2/27/2012 | 2/27/2012 | 3/1/2012 7:51:54 AM | P | PART |
|
|
See re-inspection notes listed under project related permit FIR11-00301.
|
BLD11-02589
| FIRE-Final Inspection | 2/27/2012 | 2/27/2012 | 2/27/2012 5:19:02 PM | P | PASS |
|
|
Correction items finished with the exception of single motion hardware at the back storage exit door. Lever set has been installed but does not meet a fail safe condition- tenant to provide approved style hardware at this location prior to structural final as agreed.
|
FIR12-00008
| INSP-Final Inspection | 2/27/2012 | 2/27/2012 | 2/27/2012 5:14:34 PM | P | PASS |
|
|
Verified relocated pendents at the adjacent vacant space, escutcheons installed. Fire sprinkler permit okayed for final.
|
FIR11-00408
| INSP-Final Inspection | 2/27/2012 | 2/27/2012 | 2/27/2012 5:12:17 PM | P | PASS |
|
|
Verified branchline restraints, final walkthrough passed. Permit finaled.
|
FIR11-00543
| INSP-Sprinkler Rough-in | 2/27/2012 | 2/27/2012 | 2/27/2012 5:10:36 PM | P | PART |
|
|
Remainder of overhead work at the west end of waiting 151 at the sheetrock ceiling okayed for cover- see plan set marked and initialed with today's date- contractor to provide missing hanger at one armover as discussed.
|
BLD12-00181
| FIRE-Final Inspection | 2/27/2012 | 2/27/2012 | 2/27/2012 1:59:14 PM | P | PASS |
|
|
C/N items finished. Fire life safety finaled.
|
FIR12-00097
| INSP-Final Inspection | 2/27/2012 | 2/27/2012 | 2/27/2012 1:58:38 PM | P | PASS |
|
|
Previous correction items verified for completion, scope of work passed inspection. Permit finaled.
|
BLD11-02991
| FIRE-Final Inspection | 2/27/2012 | 2/27/2012 | 2/27/2012 1:56:01 PM | P | PASS |
|
|
Fire life safety inspection completed satisfactory.
|
BLD11-01142
| FIRE-Conference | 2/27/2012 | 2/27/2012 | 2/27/2012 1:54:55 PM | P | DONE |
|
|
Gary Phone #: ###-####
|
BLD11-02991
| FIRE-Alarm Testing | 2/24/2012 | 2/27/2012 | 2/27/2012 1:54:07 PM | A | DONE |
|
|
Completed testing for the two duct smoke detectors associated with the relocated RTU's.
|
FIR12-00032
| INSP-Final Inspection | 2/24/2012 | 2/27/2012 | 2/27/2012 1:52:17 PM | A | PASS |
|
|
Final walkthrough passed. Fire sprinkler permit finaled.
|
BLD11-02801
| FIRE-Final Inspection | 2/24/2012 | 2/27/2012 | 2/27/2012 1:51:09 PM | A | PASS |
|
|
Fire life safety passed. Battery backup at two new exit signs completed today per contractor.
|
FIR11-00631
| INSP-Sprinkler Rough-in | 2/24/2012 | 2/27/2012 | 2/27/2012 1:47:50 PM | A | PART |
|
|
Overhead work at the grid ceiling areas throughout are approved for cover. Noted semi-recessed heads at rooms with sheetrock ceilings and surface mounted light fixtures to meet obstruction criteria per NFPA 13 guidelines as discussed.
|