BLD13-01935
| FIRE-Final Inspection | 2/27/2014 | 2/27/2014 | 2/27/2014 4:37:49 PM | P | PASS |
|
|
Final fire life safety inspection passed.
|
FIR14-00083
| INSP-Final Inspection | 2/26/2014 | 2/27/2014 | 2/27/2014 4:36:33 PM | P | PASS |
|
|
Fire alarm permit final approved.
|
BLD13-02294
| FIRE-Final Inspection | 2/26/2014 | 2/27/2014 | 2/27/2014 4:35:11 PM | A | PART |
|
|
C/N items completed. Final pending key box per BFD approval. Okay to occupy per G. Goldsmith.
|
FIR13-00608
| INSP-Sprinkler Rough-in | 2/26/2014 | 2/27/2014 | 2/27/2014 4:29:10 PM | A | PART |
|
|
Okayed for cover at the drop ceiling and elevator lobby sheetrock ceilings per dated approved plans.
|
FIR13-00689
| INSP-Sprinkler Rough-in | 2/26/2014 | 2/27/2014 | 2/27/2014 4:11:22 PM | A | PART |
|
|
Okay to cover 4th and 5th floor elevator lobby sheetrock ceilings as marked and dated on approved plans.
|
FIR13-00579
| INSP-Sprinkler Rough-in | 2/26/2014 | 2/27/2014 | 2/27/2014 4:06:48 PM | A | PART |
|
|
As noted on plans
|