Inspections for the day of: Monday, February 27, 2017.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMike Jordan
TitleBLD-COM/RES INSPECTOR
Phone #794-9473
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD16-04264 BLD-Final2/27/20172/27/20172/27/2017 4:31:39 PMPNR
Call 20 minutes before // Tim Phone #: ###-####
BLD16-04493 BLD-Wall Bracing2/27/20172/27/20172/27/2017 2:53:01 PMPPASS
kade Phone #: ###-####
BLD16-02414 BLD-Energy code compliance2/24/20172/27/20172/27/2017 2:35:05 PMPPASS
Foundation Insulation Phone #: ###-#### Inspection requested via web by Mike McHargue
BLD17-00152 BLD-Framing/Rough-in2/27/20172/27/20172/27/2017 1:41:52 PMPPASS
Phone #: ###-#### Inspection requested via web by Paul Gorringe.. Door infill ok.
BLD16-04242 BLD-Final2/27/20172/27/20172/27/2017 1:01:19 PMPCANC
BLD16-04242 BLD-Final2/24/20172/27/20172/27/2017 1:00:55 PMADONE
Phone #: ###-#### Inspection requested via web by Shannon Wall
BLD16-04242 DOC - Permit Finaled2/27/20172/27/20172/27/2017 1:00:46 PMPPASS
BLD16-04349 BLD-Foundation2/23/20172/27/20172/27/2017 11:44:10 AMAPART
This inspection is for a cell tower foundaition and rebar cage inspection. They will be ready at 11:00. Phone #: ###-#### Inspection requested via web by Josh Woodbeck. rebar gage ok. Will have special inspection.
BLD16-02418 BLD-Footing2/24/20172/27/20172/27/2017 10:08:01 AMAPASS
Phone #: ###-#### Inspection requested via web by Mike McHargue
BLD16-03149 BLD-Wall Bracing2/24/20172/27/20172/27/2017 9:18:43 AMANR
bob Phone #: ###-####,, verify straps on exterior. Straps not yet installed. Will reschedule whun ready.
BLD16-03762 BLD-Footing2/24/20172/27/20172/27/2017 8:56:30 AMAPEND
Jack Phone #: ###-####. Needs soils report. Footings inspected by #415.