Inspections for the day of: Monday, February 27, 2017.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Page
TitleFIRE INSPECTOR
Phone #208-914-5431
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR16-00596 INSP-Sprinkler Rough-in/Hydro2/24/20172/27/20172/27/2017 3:21:19 PMPCANC
Underground hydro rescheduled for 28FEB2017
FIR16-00596 INSP-Supply line flush2/24/20172/27/20172/27/2017 3:19:06 PMPDONE
Underground flush complete
BLD17-00072 FIRE-Final Inspection2/27/20172/27/20172/27/2017 3:18:26 PMPPASS
Previously noted items have been repaired, final life fire safety inspection passed/complete
FIR16-00573 INSP-Final Inspection2/27/20172/27/20172/27/2017 12:18:09 PMPCANC
Inspection request cancelled per conversation with Jeremy Phone #: ###-####, inspection request will be rescheduled after fire bell is installed.
FIR16-00556 INSP-Sprinkler Rough-in2/24/20172/27/20172/27/2017 11:53:29 AMACANC
3RD FLOOR tenting inspection request is rescheduled for 28FEB2017 per conversation with general contractor.
BLD16-03368 FIRE-Final Inspection2/24/20172/27/20172/27/2017 11:48:48 AMAPASS
Final fire sprinkler inspection complete, no fire alarm modifications, fire extinguishers are in common area's with current inspection tags. Final life fire safety inspection passed/complete.
BLD16-02477 FIRE-Final Inspection2/24/20172/27/20172/27/2017 9:24:36 AMAPASS
No fire sprinkler modifications (space already has quick response heads), no fire alarm modifications, fire extinguishers are in place with current inspection tags, building has knox box on west side main entry. Final life fire safety inspection passed/complete.
BLD15-01997 FIRE-Final Inspection2/27/20172/27/20172/27/2017 8:31:02 AMAPASS
Racking permit inspection complete, final for life fire safety passed/complete
BLD17-00043 FIRE-Final Inspection2/24/20172/27/20172/27/2017 8:29:40 AMAPASS
Final racking permit inspection for fire life safety passed/complete