Inspections for the day of: Tuesday, February 28, 2006.
Number of inspections: 22
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD02-02177 FIRE-Final Inspection2/28/20062/28/20063/1/2006 10:28:18 AMPDEFR
Inspection to be completed 3/1.
BLD02-02178 FIRE-Final Inspection2/28/20062/28/20063/1/2006 10:26:59 AMPDEFR
Inspection to be completed 3/1.
FIR05-00594 INSP-Sprinkler Rough-in/Hydro2/27/20062/28/20062/28/2006 3:57:54 PMPCANC
Inspection to be rescheduled due to time constraints.
FIR05-00425 INSP-Sprinkler Rough-in/Hydro2/28/20062/28/20062/28/2006 3:56:42 PMPPART
Hydrostatic test for the standpipe completed for the north and southwest stair towers, not all portions of the standpipe tested at this time.
FIR05-00666 INSP-Final Inspection2/27/20062/28/20062/28/2006 3:52:16 PMPPART
Final pending shell alarm final.
FIR05-00646 INSP-Final Inspection2/27/20062/28/20062/28/2006 3:48:26 PMPPART
Final still pending shell alarm approval.
FIR05-00685 INSP-Final Inspection2/27/20062/28/20062/28/2006 3:47:46 PMPPART
Final still pending shell alarm approval.
FIR05-00623 INSP-Final Inspection2/27/20062/28/20062/28/2006 3:46:50 PMPPART
Final still pending shell alarm approval.
FIR06-00037 INSP-Sprinkler Rough-in/Hydro2/27/20062/28/20062/28/2006 3:45:22 PMPPART
Overhead hydrostatic test is satisfactory, rough-in inspection not completed due to failure of the contractor to provide approved plans, review comments, and inspection card on site as required under condition of the permit.
FIR05-00684 INSP-Final Inspection2/27/20062/28/20062/28/2006 3:40:03 PMPPART
c/n items have been completed, final pending shell alarm permit final.
FIR05-00531 INSP-Final Inspection2/27/20062/28/20062/28/2006 3:38:53 PMPPART
c/n items are complete, final pending shell alarm permit final.
FIR05-00459 INSP-Final Inspection2/27/20062/28/20062/28/2006 3:37:07 PMPFAIL
Need to provide plan resubmittals for field review of changes as requested by previous inspection.
FIR05-00076 INSP-Final Inspection2/27/20062/28/20062/28/2006 3:34:47 PMPFAIL
Need to post building map showing roof plan including clock tower, update plans and 1st floor map to show changed EOL location from device 8:8.
BLD05-03049 FIRE-Final Inspection2/27/20062/28/20062/28/2006 12:56:20 PMAPASS
Fire life safety is satisfactory, inspection passed.
FIR05-00820 INSP-Final Inspection2/28/20062/28/20062/28/2006 12:55:00 PMAPASS
Fire sprinkler permit finaled.
FIR05-00564 INSP-Final Inspection2/27/20062/28/20062/28/2006 10:59:49 AMAFAIL
Need to provide the resubmitted plans showing relocated EOL, and possible notification in office 102 depending on occupant load for the room.
FIR05-00426 INSP-Final Inspection2/27/20062/28/20062/28/2006 10:57:13 AMAFAIL
Need to provide the resubmitted approved plans showing relocated EOL, added devices, and relocated devices.
FIR05-00852 INSP-Final Inspection2/27/20062/28/20062/28/2006 10:55:31 AMAPASS
Fire alarm permit finaled.
FIR05-00703 INSP-Final Inspection2/27/20062/28/20062/28/2006 10:54:32 AMAPASS
Fire alarm finaled.
FIR05-00702 INSP-Final Inspection2/27/20062/28/20062/28/2006 10:53:53 AMAPASS
Fire alarm finaled.
FIR05-00704 INSP-Final Inspection2/27/20062/28/20062/28/2006 10:53:18 AMAPASS
Fire alarm finaled.
FIR05-00075 INSP-Final Inspection2/27/20062/28/20062/28/2006 10:52:02 AMAPASS
c/n items have been completed, fire alarm permit for BODO #4 has beeen completed.