Inspections for the day of: Wednesday, February 28, 2018.
Number of inspections: 6
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD17-03618 FIRE-Final Inspection2/27/20182/28/20182/28/2018 1:50:24 PMPFAIL
Inspection was actually a conference. I noted that the electrical engineer shows two strobes in remodeled rooms but there is no notification elsewhere in the store. Plans may need modified to delete these devices. I noted that a FIR permit will be requierd for the two new duct smoke detectors for units 10 and 12. I will need emergency lighting provided in the pass of egress from the remodeled areas and all existing emergency fixtures functional. There is still one fire sprinkler permit for phase 1 that has not been finaled yet.

Chris Phone #: ###-####
FIR16-00785 INSP-Supply line flush2/27/20182/28/20182/28/2018 1:44:21 PMPPASS
Underground supply line flush passsed
FIR18-00050 INSP-Final Inspection2/28/20182/28/20182/28/2018 1:14:12 PMPPASS
permit finaled
FIR18-00141 INSP-Sprinkler Rough-in2/26/20182/28/20182/28/2018 9:50:41 AMAPASS
Piping rough-in and tenting inspection passed. Piping can be covered.
FIR18-00145 INSP-Final Inspection2/28/20182/28/20182/28/2018 9:12:58 AMAPASS
Permit finaled


ADAM CHITWOOD Phone #: ###-#### Inspection requested via web by Brodie Stenquist
BLD17-03941 FIRE-Final Inspection2/27/20182/28/20182/28/2018 8:21:07 AMACANC
to be canceled per Jason Phone #: ###-####