Inspections for the day of: Thursday, February 28, 2019.
Number of inspections: 5
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorEric Story
TitleELE-INSPECTOR
Phone #985-3493
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE19-00720 Final2/28/20192/28/20192/28/2019 11:13:34 AMPPASS
Phone #: ###-#### Inspection requested via web by Same Electric
Service change final ok
MIS19-00056 ELE-Final2/28/20192/28/20192/28/2019 11:13:11 AMPDONE
confirm no electrical
No work being done at this time, once remodel starts in back area lights will be change out and a permit will be issued to a licensed contractor
ELE19-00687 Electrical Rough-In2/27/20192/28/20192/28/2019 10:56:43 AMAPASS
Keith Phone #: ###-####
Main hall bath and back baths and misc walls in beds ok to cover
ELE19-00272 Final2/27/20192/28/20192/28/2019 9:56:49 AMAPASS
solar install ready for inspection; approved plans on site; all work done according to the stamped plans; except for the taps inside the electrical panel, all work is surface/exterior. The solar equipment and meter are in the back yard directly under the array.
Call me at 850.8965 before you head to the site, and I''ll arrange someone to be there to get you access inside/back yard.
thanks guys Phone #: ###-#### Inspection requested via web by Ryan King
Solar Array final ok
ELE19-00205 Conference2/27/20192/28/20192/28/2019 9:54:43 AMADONE
please call before arriving Lee Phone #: ###-####
Discussed service requirements and IDPCO for meter.
Owner will drop meter for IDPCO and install a 100 main breaker panel or meter main or find a listed tie down for SQD breaker in a GE panelboard