Inspections for the day of: Monday, February 29, 2016.
Number of inspections: 12
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR16-00124 INSP-Final Inspection2/29/20162/29/20162/29/2016 3:32:12 PMPPASS
Permit finaled
FIR16-00022 INSP-Sprinkler Rough-in/Hydro2/26/20162/29/20162/29/2016 2:47:57 PMPPASS
Overhead hydro passed
FIR15-00715 INSP-Sprinkler Rough-in/Hydro2/26/20162/29/20162/29/2016 2:34:15 PMPPASS
Overhead hydro test passed.
FIR15-00716 INSP-Sprinkler Rough-in/Hydro2/26/20162/29/20162/29/2016 2:31:40 PMPPASS
Overhead hydro test passed.
FIR15-00717 INSP-Sprinkler Rough-in/Hydro2/26/20162/29/20162/29/2016 2:31:07 PMPPASS
Overhead hydro test passed.
BLD16-00183 FIRE-Final Inspection2/29/20162/29/20162/29/2016 2:26:40 PMPFAIL
Provide exit signage as per the city approved plans. All other items appear ok.
MIS16-00054 FIR-Conference2/26/20162/29/20162/29/2016 2:06:20 PMADONE
I met and spoke to Gracie Garcia about the need to get an occupancy permit applied for and issued so that the associated inspection could be performed. I set up a follow up inspection for two weeks from now.
FIR16-00032 INSP-Final Inspection2/29/20162/29/20162/29/2016 12:07:32 PMPPASS
Permit finaled
BLD15-04138 FIRE-Final Inspection2/26/20162/29/20162/29/2016 10:11:46 AMPPART
A temporay occupancy is being given with Scott's permission. As per the fire code review comments, a 1 hour wall needs to be provided. It does not appear that "house keeping" should be an issue due to construction type and size of the booth. Per ESI superintendant the wall will be installed with-in the two week time period for a temporary occupancy. A follow up inspection for myself has been scheduled.
FIR16-00123 INSP-Final Inspection2/26/20162/29/20162/29/2016 10:01:56 AMPPASS
Permit finaled
FIR16-00104 INSP-Sprinkler Rough-in2/26/20162/29/20162/29/2016 8:21:12 AMAPASS
Remaining underground is ok to cover on the east building.
BLD15-02395 FIRE-Final Inspection2/26/20162/29/20162/29/2016 8:20:15 AMAPASS
Life safety passed. Contractor to get plan review approval for deleting the east exit door prior to a building signoff.