BLD00-02242
| BLD-Aging Inspection | 2/3/2003 | 2/3/2003 | 2/3/2003 12:00:00 AM | | DONE |
|
|
|
MIS02-00047
| BLD-Final | 1/30/2003 | 2/3/2003 | 2/3/2003 12:00:00 AM | A | NR |
|
|
jennette; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie verify fire 2/3/2003 2:31:39 PM
|
BLD02-02984
| BLD-Other | 1/31/2003 | 2/3/2003 | 2/3/2003 12:00:00 AM | A | NR |
|
|
Scheduled by a contractor via Hello! on 01/31/2003 at 09:08:43. Contact: ###-####....need fire sprinkler r/i before tiles at lid 2/3/2003 11:02:44 AM
|
BLD02-02915
| BLD-Energy code compliance | 1/31/2003 | 2/3/2003 | 2/3/2003 12:00:00 AM | A | PART |
|
|
jeff; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie...walls ok, deck framing ok. 2/3/2003 9:54:46 AM
|
BLD02-00172
| BLD-Final | 2/3/2003 | 2/3/2003 | 2/3/2003 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 02/03/2003 at 07:35:53. Contact: ###-####....Modified "phase 1" ok for c/o. 2/3/2003 3:05:06 PM
|
MIS02-00047
| BLD-Final | 2/3/2003 | 2/3/2003 | 2/3/2003 12:00:00 AM | P | PASS |
|
|
fire ok 2/3/2003 3:08:58 PM
|
BLD02-01843
| BLD-Footing | 2/3/2003 | 2/3/2003 | 2/3/2003 12:00:00 AM | P | PART |
|
|
###-####... garage ftgs poured, front verts in...no one onsite, looks ok 2/3/2003 3:14:13 PM
|
BLD02-01164
| BLD-Conference | 2/3/2003 | 2/3/2003 | 2/3/2003 12:00:00 AM | P | PASS |
|
|
###-#### Needs more time work still in progress...wip 2/3/2003 5:01:54 PM
|
BLD02-02984
| BLD-Framing/Rough-in | 2/3/2003 | 2/3/2003 | 2/3/2003 12:00:00 AM | P | PART |
|
|
grid... c/n, ok to continue, add struts 2/3/2003 5:03:00 PM
|